|
Building
on Battery Wharf
by Clair D. Urbain
Skanska USA Building
Inc. takes on the elements and logistics to build luxury on Boston’s
historic waterfront.
With tremendous respect
for history, Boston is a vibrant city that keeps one eye on its
future while the other eye guards its great past.
Perhaps that’s one of
the reasons the Battery Wharf on the city’s North End only recently
has undergone revitalization. The wharf is made up of a granite
block seawall that dates back to the 1800s and, until recently,
proposed a formidable challenge to developers: How can you take
advantage of the land and harbor sides of the historic seawall
without removing it, damaging it or modifying it?
|
|
|
The
original seawall is easily seen in this preconstruction
photo. Engineers and architects vowed to maintain the wall’s
integrity, adding time and expense to the construction
project. |
|
|
Most recently, it was a
seafood processing plant and retail facility for Bay State Lobster,
a Dunkin’ Donuts store and a parking lot. Today, the site is
undergoing a $275 million revitalization in the heart of one of
Boston’s oldest neighborhoods.
The 807'-long seawall,
although not formally listed on any historic register or protected
by any formal agency, is being preserved, albeit at considerable
design and expense. Even more surprising, the only way the historic
seawall may be seen when the project is finished is in a boat at low
tide.
Nearly 50 percent
complete, the site is a beehive of activity as general contractor,
Skanska USA Building Inc., transforms the site into a mixed-use
property with retail establishments, luxury hotel and meeting
center, high-end condominiums and parking garage. The four-building
Battery Wharf complex will rest on both sides of the wharf, with two
buildings sitting on piers driven into the harbor with foundations
that carry the weight over the seawall. Two other buildings sit on
the back side of the seawall. It will appear to be one 485,000 sq.
ft. property, says Kerim Evin, senior vice president and operations
manager for Skanska’s Boston office. He is also the project
executive for this ambitious building project due to open early in
2008.
“This project presents
numerous challenges. We’ve had to deal with weather and seasonal
tides throughout construction, tight site logistics and unforeseen
soil issues that affected our earth support and excavation,” says
Evin.
Weather and tide
Just as the 12'-high historic seawall protects the shoreline from
the pounding waves brought on by weather and tidal forces, the
buildings’ design must allow the wall to remain in place without
significant alteration. To accomplish that, the support structures
of two of the buildings that will make up the five-star Regent
Boston Hotel and luxury condominiums must bridge the seawall without
resting on it or modifying it in any significant way.
|
|
|
Progress
continues on the harbor-side buildings of the wharf while
crews begin to excavate 45' of soil out of the land side of
the project in early 2006. Note the precast concrete forms
on the harbor side and the horizontal supports in the right
side of the picture. The supports were needed to assure
safety and productivity during excavation. Meanwhile,
equipment and supplies could only be delivered to the
harbor-side buildings via the narrow alley on the right side
of the picture. |
|
|
On the harbor side,
pilings were driven up to 110' deep and then precast concrete forms
were laid across them to straddle the seawall. They also carry the
foundation to the land side of the wall.
“These precast forms
were then filled with concrete to complete the foundations of the
buildings that extend over the seawall,” explains Evin. “In some of
the forms, utilities were located inside them and then encased in
concrete. This solved some of the space issues involved with the
buildings on the harbor side. The precast wharf was redesigned,
which ultimately saved about $.75 million in construction costs,”
Evin says.
The steel pilings
adjacent to the seawall had to be notched to allow the beams’
precast forms to reach the foundation on the land side.
“These notches lowered
the level of protection from high tide and high winds, which could
push water over the seawall and into the foundation. We sealed the
gaps with hydraulic cement to keep the hole from getting flooded.
That really worked well,” he says.
|
|
|
This
circular atrium opening in the street will allow light into
the lower levels of The Regent, a luxury hotel that will
have meeting rooms below grade. It also shows the amount of
work that had to be completed before heavy equipment such as
delivery trucks could drive over the excavated area to make
deliveries to the harbor-side buildings under construction. |
|
|
On the land side of the
wall, the facility required excavation of up to 45' of soil to make
room for the hotel’s meeting rooms, back-of-house functions and
parking garage. Water infiltration from the harbor was a great
concern.
“We originally proposed
eliminating the cast-in-place concrete foundation wall and having
the vertical sheet piling serve as a permanent wall and becoming an
integral part of the buildings’ foundations. While this is
practically unheard of in the United States, it is more common in
Europe and would have saved nearly $3 million in construction costs.
However, the engineers involved with the project’s design weren’t
sold on the concept and elected to install the pilings, then pour a
30"-thick foundation wall as originally designed.
“It would take more than
three months to pour the foundation as originally designed, which
would have held up the rest of the building,” says Evin.
To overcome that
challenge, Skanska proposed extending the steel framework down to
the footings so construction could continue above ground while crews
came back and used mobile gang forms to pour the foundation below
ground. “The foundation is poured right around the steel frame. It
becomes a part of the foundation. There was an additional cost to
this method, but it took the foundation out of the critical path and
allowed building to proceed. It more than paid for itself in cost
savings associated with time,” says Evin.
The tidal pressure also
caused some tense times. While excavating the area for the southwest
corner of the site, one of the sheet pilings failed and flooded the
excavation. “We lost three pieces of construction equipment in that
flood. Divers located where the failure occurred so we could fix it
and then we pumped the hole. That happened on a Friday night, and we
were excavating again by Wednesday. It looked catastrophic, but it
didn’t affect our schedule as much as we thought it would.”
While beginning
construction on the concrete wharf, it appeared that the concrete
piles and sheet piles were exhibiting signs of movement. In some
cases, they moved 8". It was presumed tidal action was causing this
movement, but it was never fully explained by the engineers. “We had
to sit tight on fabricating the wharf elements for a short time
while they settled down, which they did. Fortunately, the deviation
didn’t affect the scheduled placement of the precast concrete
forms,” Evin says.
“As excavation continued
for the building on the northwest corner of the property, unstable
soil conditions and extremely tough pile-driving conditions slowed
progress. We ended up having to add braces in the excavation to
stabilize the perimeter pilings and install grout curtains to ensure
water cutoff. This caused us to completely re-sequence the erection
of the buildings,” says Evin.
|
|
|
Steel
workers continue to place beams on the northwest building as
the other three buildings get closer to completion.
Originally, this building was to go up first, but
challenging soil conditions and jobsite logistics required
turning the schedule upside down and proceeding with work on
the harbor-side buildings. |
|
|
Jobsite logistics
Due to the delayed excavation on the northwest building, crews
gained momentum on the buildings on the harbor side of the project.
This created logistics problems throughout the site.
“The street that bisects
the site is built over the meeting rooms, parking garage and
back-of-house areas, so it couldn’t be used to move equipment until
major portions of the foundation and structure were in place. That
meant we could only feed equipment and materials onto the site
through a 12'-wide access point on the north side of the property.
Even then, we had to create reinforcements to support some of the
heavy equipment that needed to get back there,” he says.
Although the street
bisecting the site can now support truck and other vehicle traffic,
the various crafts working on the buildings are requiring supplies
and equipment deliveries in a timely fashion. The Boston Police
department has a traffic detail on the site to maintain traffic flow
around the large trucks delivering goods.
“We even brought in an
extra crane to place utility enclosures on the rooftops of the two
harbor-side buildings because we didn’t want to take time away from
the other crane that’s placing steel for the northwest building,” he
says. The work continues like clockwork as windows are installed,
mechanicals, electrical and plumbing are roughed in and drywall is
hung.
“It’s a bit more
complicated because the floor-to-floor height in the buildings is
9'2" but the finished ceiling height is 7'6". That’s not much room
to run mechanicals and they must all fit in the ceiling,” he says.
Building material prices
have also played havoc with the project, but by working in a
design-assist fashion on certain portions of the project, Skanska
subcontractors have been able to reduce the impact of the increases.
“We have been hit by two
irregular material price hikes, mainly in structural steel, copper
and petroleum-based products. By working under a design-assist
structure for some parts of the job, it is the only way we could
look for savings to offset the rising cost of material,” Evin says.
|
Jobsite
specs:
Type: Mixed-use commercial and residential
complex featuring a 144-room luxury hotel with meeting
rooms, 103 residences, retail establishments and a 376-space
parking garage.
Size:
485,000 sq. ft. total land area with two five- and two
six-story structures with meeting rooms, back-of-house
facilities and a parking structure on two levels below
ground and harbor level. Cars are valet-parked in stacked
spaces that accommodate two cars/space.
Total
Cost: $275 million. Residential space priced for
sale at $1,200 to $1,300 per sq. ft. with monthly
condominium fees at approximately $1/sq. ft.; parking
available for $125,000/space. |
Published in the July/August 2007 issue of
Contractor Tools and Supplies
magazine.
back
to top
|