|
Capture
the wind
Mortenson
Construction helps Orion Energy harness the wind by constructing 100
wind turbines in central Illinois. The remote location requires a
close eye on logistics and a total commitment to safety.
by Clair D. Urbain
What goes around, comes
around. Prairie pioneers quickly understood that if they could
harness the unrelenting winds that blew across their fields, they
could easily pump water and even power other mechanical marvels of
the day, assuring a better life on the frontier.
In the new millennium,
the same is true, but with a different twist. Instead of spindly
windmills catching a breeze only 50' or 60' in the air, behemoth
125,000 lb. wind turbines are perched on 262' pedestals to convert
wind into electrical energy. Increasingly, these wind turbines are
sprouting up across rural counties, harvesting winds while farmers
continue to harvest crops below them.
Mortenson Construction,
based in Minneapolis, Minnesota, is no stranger to these types of
projects. It is presently working on its 58th wind farm, installing
100 wind generators over 50 square miles in Stark and Marshall
Counties in central Illinois for Orion Energy on its Camp Grove Wind
Farm.
Working on a
construction site that covers more than 50 square miles in rural
Illinois presents some interesting logistics challenges and unique
safety concerns that Mortenson crews take seriously, says David
Dreis, Mortenson’s Energy Group project superintendent on the site.
From concrete foundation to rotor blade, Mortenson crews plan every
move for safety, quality and efficiency.
What looks simply as a
column rising nearly 262' in the air is much more complicated than
that. Each turbine has a complex and uniquely designed concrete base
to anchor the wind turbine, provide adequate grounding for lightning
protection and a way to route the harnessed electrical energy into
an underground electrical grid that feeds into a substation, says
Dreis.
Foundation work starts
with an excavation that is a 54' or 55' square with benched walls.
All are sloped as determined by soil type to provide worker safety.
Each excavation has ramps for worker egress.
“The towers’ foundations
are octagonal and very wide at the bottom. The depth is based on the
soil conditions and some of them must be as deep as 9' and up to 50'
in diameter at the base. The foundation culminates at a 17'-diameter
pedestal at the ground surface,” says Dreis.
“There is a double mat
of rebar. The bottom section is at the base of the foundation and
the other follows the contour of the base to the surface. They also
have an elaborate grounding system that is part of the foundation to
help protect the wind turbine from damage caused by lightning
strikes. It’s all connected to an embedded plate at the bottom of
the unit,” Dreis explains.
Rebar installation
Two crews install rebar: one crew assembles the top mat and bottom
mat, then a bolt cage crew places the bolts. The towers are anchored
to the foundation with 140 1 7/8" bolts that run the full depth of
the foundation. They are held in place at the base and top with a
template and are also fixed in position to keep them centered and
stable during concrete pouring.
The foundation concrete
is a 5,000 or 6,000 psi mix. “We have subcontracted a batch plant
and all of its trucks are dedicated to our placements. They know our
traffic patterns and we get fast turnaround so the concrete gets
placed fresh. We will place about 1,100 cu. yd. a day,” he says.
Once the concrete cures,
another crew installs the towers and turbines. “All components come
in by truck. The towers come in three pieces as a base, intermediate
and top section. The nacelle and hub with blades are shipped
individually, assembled onsite and then lifted into position as one
unit.
“The base section is
lifted into place, then the base is grouted. The intermediate
section is set after the grout is placed. Once the grout has reached
its design strength, the top section, turbine nacelle and rotor are
installed.
“We use a Manitowoc
16000 and a Liebherr LR1400 crane for the base and intermediate
section setting. We are also using the Liebherr unit on two of the
most remote towers. We will set the base and midsection, then
reconfigure it to set the top section, nacelle and rotor,” Dreis
explains.
“On the others, we will
use the Manitowoc 2250 crane for base and midsections and then use
the Manitowoc 16000 to set the top tower section, nacelle and rotor.
We use a triple deuce (222) Manitowoc to assemble the hub. The
blades are connected to the hub on the ground.
“They can go up fast,
but we can be hindered by weather. Rain without lightning is okay,
but wind is our biggest challenge. The wind speed and gusts affect
the crane’s load capacity, so we have to be always aware of it. We
can be delayed for days because of wind. Fall and spring are
unpredictable and, in the winter, it’s always windy. Summer is the
best time to erect,” he says.
Moving equipment across
county roads requires extensive planning. Most of these
farm-to-market roads aren’t built to take these heavy loads, so
Mortenson had to map every route to every site for deliveries and
crane movements.
“We self-perform most of
the work, but have a subcontractor handle the electrical portion. We
work with two electrical contractors: one for turbine wiring and
underground connection work and another for the overhead
transmission line and substation work.”
Fast installation
“The conduit is prefabricated so it installs quickly. Crews can do
as many as four turbines a day. The conduit comes up through the
center of the foundation that provides a run outside the tower to a
pad where a transformer sits. The wiring for the nacelle is also
prefabricated and is already inside the tower when it is set in
place. Only a small whip goes up into the nacelle.
“All wiring from the
transformer to the substation is underground. The large-diameter
cable that carries the power from the sites to the power grid is
buried between 4' and 5' deep. The wind turbines are connected,
point to point, in seven underground circuits that feed into the
substation,” he says.
“M. A. (Mort) Mortenson
Jr., the owner of Mortenson Construction, is unwavering about
safety. He firmly believes that if you first take care of safety,
quality and efficiency will follow,” Dreis says.
Every worker on any
Mortenson jobsite goes through Mortenson’s orientation. It is made
up of three segments: the first one, which is the longest, takes
almost two hours. It is very site-specific to wind farm
construction. The second and third sessions are shorter and
reinforce all of the training presented in the first session. “We
use a combination of classroom and hands-on training. Sessions are
held on the first three weeks the worker is on the job.
“Safety is everything to
us. We are a zero-injury company and we really mean zero injuries!
We do everything we can to eliminate even the small risks. We start
with orientation and follow up with ongoing training. We also
practice empowerment. If any worker sees anything that’s an unsafe
act or condition, they can stop the job and get it addressed. Most
of these are taken care of by the workers or with their team
members,” he says.
Jobsite stretch
Unlike most all other jobsites, Mortenson crews start the day with a
10-minute session of stretching and bending. All workers are
required to do this exercise that warms up muscles and limbers up
joints from head to toe. “We do this to reduce soft-tissue injuries
and we haven’t had any. After all, athletes stretch before games,
why not workers doing physical labor?” asks Dreis.
After the warm-up
exercises, crews go through a 20-minute review of the day’s
activities. “They plan their days as a team. They work through a
hazard recognition card together, listing tasks to be completed and
what needs to be done to do their jobs safely. They review any near
misses on tasks as well and discuss them,” says Dreis, who reviews
these cards daily.
“To encourage filling
out the cards, we have a drawing for a $50 gift card every week. If
the hazard analysis card is turned in, any worker’s name on it is
eligible for that week’s drawing,” he says.
The hazard analysis card
outlines how the team will do the job, forecast risks, and then plan
for them. It covers every step of the task. “Just saying ‘be safe’
is not a control measure,” Dreis points out.
“I look at the cards to
see if any trends are developing. The cards cover tool inspections,
equipment problems, or whether special permits that are needed had
been obtained, to name a few. Each team identifies and works through
the hazards.
“The cards don’t have to
be in perfect English or have perfect spelling, but we do want them
to be thought out. Typically, we review 25 or 30 cards a week. They
note on the card whether they or the work team corrected the issue
or if it’s something I need to get involved with,” he says.
With the variety of
tasks taking place, several work crews are spread out over the 50
sq.-mile jobsite. “We have several types of work crews and they
change as the job changes. We have excavation, foundation, offload,
clean tower, set base/midsection, build rotor, main erection, crane
walkers and final grade crews. We also have two-man de-watering
crews because we routinely encounter groundwater. We always send at
least two guys out per site and each site has at least one radio. No
one works alone,” he says.
Mortenson has a first
responder system in place. “We have not used it for a company
emergency, but we have used it with two local accidents and with one
delivery person who thought he was having a heart attack. In all
cases, we had medics on the site within 11 minutes from towns that
are five or six miles from the site. We have planned for this and
set up traffic control. We work closely with local first responders
so they know what to expect and where to go. As the job progresses,
we conduct mock runs that test our first responder system. Our first
one focused on carpenter/laborers, then we conducted another for
millwrights and iron workers. As the trades change on the job, we
modify the mock run to test the response that would be needed for
the type of accident that may occur with that trade,” he says.
Operational in 2008
The crews broke ground in early 2007 and plans are in place to have
the turbines producing enough electricity to power up to 45,000
homes by early 2008. The sophisticated units each produce up to 1.5
MW, turning with only 8 or 9 mph winds. The turbines’ blades rotate
in the hub to take best advantage of the wind speed. The units will
shut off at wind speeds greater than 35 or 40 mph.
With proper planning and
commitment to safety, the early-2008 power-up date is definitely
achievable.
Click here to
see more images of tower construction at the site.
Published
in the November/December 2007 issue of
Contractor Tools and Supplies
magazine.
back
to top
|