|
New
lease on life
Taking a ’60s-era
building to its core, work is underway to create the Constitution
Center, which promises to be the largest Gold-certified LEED
building in the United States.
by Clair D. Urbain
The U.S. Department of
Transportation building is undergoing a tremendous transformation.
The building has been stripped of its former, albeit aged, beauty
and function as it undergoes a metropolitan metamorphosis. It’s
being replaced by a building design that better reflects the new
millennium need for greater security, information and energy
efficiency. Even the building is being renamed Constitution Center,
signifying its new lease on life.
Plus, it’s very likely
going to achieve Gold level Leadership in Energy and Environmental
Design (LEED) certification. That’s the goal of building owner David
Nassif Associates, reports Tim Jaroch, managing general partner.
“Since this building
will likely have government tenants, what we can charge for rent is
largely proscribed. But having the Gold level LEED (NC)
certification gives us a competitive advantage vs. other buildings.
It can only help us market the building,” he says.
There are two types of
LEED certifications: Commercial Interiors (CI) and New Construction
(NC), which covers the base building and renovations. At the
Constitution Center, it will be up to the tenant to achieve LEED CI
certification. “It is entirely in their hands as to what level they
would like to achieve,” says Jaroch.
The ambitious LEED Gold
(NC) rating is possible with the combination of great location and
close attention to detail. Several LEED points are gained because
the building has a Metro station built into it; other points are
achieved because it is a renovation rather than new construction.
 |
|
The
former Department of Transportation building in
Washington, D.C. is undergoing a metropolitan
metamorphosis to become the Constitution Center, a
Level IV blast-resistant building that uses chilled
beam technology to heat and cool the building.
Widely used in Europe, this is the first large-scale
installation in the United States and promises to be
more effective and efficient than conventional HVAC
systems. |
|
The demolition process
required careful management and tracking to assure the bulk of the
material was being recycled, says Jamie Pacala, James G. Davis
(Davis) Construction assistant project manager who is coordinating
LEED efforts.
“We are above 76 percent
recycling at this point on the site. Unfortunately, any finished
painted wall couldn’t be recycled, but all of the carpet was able to
be recycled. All metal that could be recycled was separated on the
site,” he says.
The carrera marble
exterior is being recycled into a sand/marble mix that’s sought
after by area golf courses for paths and sand traps.
“In the LEED process, we
can track recycling by the cost of the materials or by its weight.
We did it by the weight of the material. It is difficult, and much
of it is up to the demolition contractor. To this point, we have
produced 24,000 tons of debris and have recycled 18,380 tons. LEED
awards one point for 50 percent recycling and two points for 75
percent or more recycling of construction waste,” Pacala says.
Let the demolition begin
In total, the project covers more than 2.1 million sq. ft.
Demolition of the 40-year-old façade and interior began in July
2007.
 |
|
Davis
team members, left to right, front row: Brad Cordek,
Jamie Pacala. Back row: Tony Lee, Ted Holt, Bill
Bundens. |
|
Inside and out, the
building was gutted to its basic frame to install an
energy-efficient infrastructure and to rebuild the structure to meet
strict Level IV blast resistance standards, says Ted Holt, Davis
Construction project executive.
“We have stripped it to
its shell, keeping its core elevators. The old building was an
Edward Durrell Stone design, who also designed the Kennedy Center,
and was built in the late ’60s. Its exterior was made up of 2'-wide
panels of white carrera marble separated by narrow windows, which
allowed little natural light inside the building. It also blocked
many of the great views of the Capitol area. While marble was an
economical building material at the time, it didn’t age well,” says
Holt.
Hysteresis is the
culprit in the marble panels’ deterioration over time. “The panels
develop minute cracks due to heating and cooling cycles from the
sun’s rays and the heating and air conditioning inside the building.
Moisture then works its way into the cracks, causing the marble
panels to bow and eventually pop out of their mounts or crumble.
Once this process begins, it’s irreversible. The building required a
full-time mason to maintain the exterior and, after 30 or 40 years,
the exterior marble was buckling and in danger of falling off,” says
Tony Lee, senior superintendent for Davis Construction.
Surprisingly, the marble
façade was easy to remove. Working from swing stage scaffolds,
workers used 3-lb. sledges to crack the marble which fell to a bed
of sand below.
The block-square
building has a 90,000 sq. ft. courtyard and had 24 miles of interior
walls that had to be stripped to the core, says Holt. “The building
has 21 elevators that have to be modified, and four new elevators
are being added to service the office floors. We will also add six
shuttle elevators that will take building occupants from the
three-level basement garage to the lobby level. It’s part of the
advanced building security features that developed since the
Oklahoma City and 9/11 incidents,” says Holt.
As crews removed the
exterior and interior of the building, the demolition subcontractors
had to work in concert to remove debris.
The typical floor
structural load capacity was such that skid-steer loaders couldn’t
cross paths within the same floors and, as material dropped down
trash chutes, they couldn’t work over top of each other. “We had
full-time monitors direct traffic between floors. Nothing went out
of the building or down the trash chutes without a Davis team member
directing the work,” says Brad Cordek, Davis assistant project
manager.
“We used the courtyard
to gather and sort the debris. We dropped the debris from opposite
corners of the building into the courtyard, and approached the work
at 90 degrees from floor to floor for safety. It also spread the
load of the working equipment so it would not overload the
structure,” says Lee.
Once pushed into the
courtyard, debris was sorted and hauled to 53' trailers on E Street.
“The demolition subcontractors used wheel loaders to move the
debris, and carefully selected them so their weight would not exceed
the weight-bearing capacity of the courtyard and garage below,” says
Lee.
The parking garage under
the 5 1/2-acre facility is three levels deep and provides 15 acres
in total space. “We added shoring in three levels of the garage to
support the sorting in the courtyard,” says Cordek.
Although demolition is
almost complete, structural limits continue to affect the project.
Because of the tight perimeter of the site, the tower cranes must
sit on the existing substructure. A large, steel-framed base was
constructed to transfer the crane loads to the concrete building
structure below. “With Holbert-Apple, a local structural engineering
firm, we designed a tower crane base similar to what we’ve done on
other renovations,” says Holt.
Reflecting the Davis
commitment to safety, lock-out/tag-out protocol during demolition
takes top priority on the site. Contractors follow a simple visual
checklist to determine if power, water, cooling/heating lines and
other infrastructures could be demolished.
“For temporary power and
light, we had the electrician run temporary risers in each quadrant
of the building in the old electrical rooms. For lighting, we used
Wobble Light temporary work lights until the ceiling was removed.
Since this is a renovation project, key water, sewer, elevators, and
power had to remain live,” says Bill Bundens, Davis MEP project
manager. “We used a standard marking on all utilities. If it was
marked red, it meant, ‘Do not touch!’ If it was marked green, it
could be removed. Everything was tagged and if anyone came across
something that was not marked, it was assumed it was live and could
not be touched until it was checked out and marked,” says Lee.
“We went with hi-vis
safety vests on the site so Bobcat loader and other equipment
operators can see all workers more easily. Even though demolition is
nearly complete, we continue to wear the high-visibility vests,”
says Bundens.
The previous HVAC system
used ethylene glycol, which also had to be removed efficiently and
safely. “During demolition, we had meetings with all of the
contractors every Monday, Wednesday and Friday to coordinate all of
the activity,” says Lee.
Blast resistance
To meet the needs of a greater pool of potential tenants, a Level IV
blast rating design was incorporated into the new building façade.
The all-glass curtain wall provides energy efficiency and panoramic
views of the Capitol and surrounding area.
 |
|
The
new building exterior is energy-efficient glass that
offers blast resistance and opens up panoramic views
of the Capitol and surrounding area. |
|
The curtain wall was
developed as a design-assist project. “We all worked with Enclose
Corp. (subcontractor), SmithGroup (architect), Weidlinger Associates
(blast consultant), SK&A (structural engineer), and Wiss, Janney,
Elstner Associates (enclosure consultant) to develop a custom
anchoring system that can be installed efficiently and works with
the existing structure,” says Holt.
 |
|
Curtain wall window panels hang from these mounts.
The original concrete mounts had to be removed and
replaced to meet Blast IV standards. |
|
Previously, the marble
panels were held in place by concrete lugs spaced every 5' on
center. The old lugs had to be removed, then more than 30,000 anchor
bolts were epoxied into the façade of the building. To meet blast
requirements, new street-side anchors are nearly twice the size of
other anchors, and the courtyard anchors are designed to withstand
blast forces. Once anchors are installed, aluminum anchors mount to
these and then the glass panel clips onto them.
“Each glass panel unit
is 5' wide and two stories high. Once the preparation work is in
place, the glass goes up very fast,” says Holt. “This is repetitive
work by nature, so once workers get past the quarter- or half-way
point, production really increases because workers know what to
expect.”
In the rest of the
building, a variety of changes beef up its ability to absorb a
blast. “All occupied areas of the building are protected, and the
key garage structural elements and mechanical, electrical and
plumbing system rooms have been hardened,” says Holt.
Heating and cooling system
Although widely used in Europe, chilled beam HVAC systems are a
relatively new technology in the United States. The systems being
installed in the building will lower heating and cooling costs
significantly, and along with other factors, will result in a
payback period of less than four years, says Jaroch.
SmithGroup, the
architect/engineer on the project, suggested using this technology.
More than 10,000 chilled beam systems are in use in Europe. Several
manufacturers were considered, and
TROX was
selected.
Chilled beam HVAC
systems use induction to transfer heat or cooling from water pumped
through the system instead of a heat exchanger in a chamber in a
forced air system. To fully test the chilled beam concept in
Washington’s highly variable weather, the owner installed three
different chilled beam systems in a controlled mock-up area in the
penthouse before demolition began and collected data for more than a
year. This data was instrumental toward the decision to select TROX.
“The units use induction and about 10 percent of the air flow of
conventional systems. It conditions air already in the building at a
fraction of the cost,” says Bundens.
“This is the largest
chilled beam installation in the United States. It uses units that
are only 5" deep, a big plus where the space between the floor to
the underside of the next floor is only 9'4". Most TROX units are
12" deep, and that’s the entire depth of our dropped ceiling plenum.
We worked closely with the manufacturer, to develop a 5"-deep system
that fits within our dropped ceiling plenum along with all of the
other utilities. Its central plant is located within the penthouse
and eliminates the need for separate HVAC systems on every floor in
each quadrant. That opens up significant rentable space on every
floor,” Bundens says.
|
Big Chill |
 |

Chilled beam runs were specially engineered to be no
more than 5" thick, maximizing dropped ceiling
space. |
|
The system moves a
fraction of the air needed for other systems because water delivers
heat faster than air, dispersing heat with water at a 10:1 ratio. “A
conventional system moves 100 cfm; this system moves no more than 10
cfm, depending on demand. There are no moving parts in the units
placed in the tenant spaces. There will be 6,600 of these units in
the building, and they can be zoned with three to five of them
together on this job,” Bundens says. He adds it is much more energy
efficient than other systems. “As electricity goes up in price, it
is much more efficient to use water to displace heat and introduce
cooling through water than it is with air.”
Dan Donaghy, project
manager for Pierce Associates, the mechanical contractor on the
project, says this is the first chilled beam system Pierce has
installed. “Installing the new system is not that much different
from installing a conventional system except that it offers better
unit accessibility once installed. The coil is inset into the
finished and exposed sheet metal box and it can be accessed without
removing the ceiling. There is also a cost savings because of the
smaller ducting that’s needed and lower airflow means smaller units
that take less power to operate. It’s an efficient system because it
doesn’t blow new air in, it just combines and tempers air presently
in the room,” Donaghy says.
The previous 50,000 sq.
ft. penthouse had to double in size to accommodate the building’s
newly installed systems, which include chillers, heat exchangers,
cooling towers, boilers, electrical switchgear, emergency gen sets
and other building support equipment.
“We had to spread the
weight of the equipment across the building’s structure,” says Holt.
SmithGroup used Building Information Modeling (BIM) in preparing the
construction contract documents, but cost and time restraints
limited the team’s ability to use it in the shop drawing process.
It’s a useful tool if the right amount of time is put into it on the
front end.
“It was helpful to a
point, but it must be done at the shop drawing level for greatest
effect. Contract drawings will pick up the big conflicts, but using
BIM on the shop drawings allows the team to catch the nuances that
are difficult to see in two dimensions, such as the locations of
valves and gauges for long-term servicing of the equipment. It also
needs to be across all disciplines. If the mechanical and plumbing
contractor use BIM but the sprinkler contractor doesn’t, you lose
some tremendous efficiencies,” says Bundens.
The team has worked
together to prefabricate the risers for each quadrant. “The piping
risers are delivered to the site complete in 40' sections. We
settled on that length because that’s the maximum height the crane
can lift, the sections fit on a standard flatbed truck, and it
closely matches standard lengths of stock piping. We believe the
fabricated units are manufactured under much better quality control
and the onsite installations go faster. The turnouts have already
been completed, so it's simple to tie them into each floor,” says
Holt.
Published
in the July/August 2008 issue of
Contractor Tools and Supplies
magazine.
back
to top
|