|
Digging
deep on the strip
by Clair D. Urbain
Developers are digging deeper and
building taller than ever before on Las Vegas Boulevard, changing
the face of the Las Vegas Strip.
You wouldn’t expect water problems in
Las Vegas, which gets on average less than 6" of rain per year. But
if you dig more than 16' below the surface, you’ll quickly run into
groundwater that, until now, has discouraged casinos and hotel
developers from digging deeper on some of the country’s most
valuable real estate. But just like the skyline of Vegas, that’s
also changing.
“Las Vegas is becoming more urban in its
construction methods,” reports Steve DeWees, Perini Building Company
project executive who is responsible for the $3 billion Cosmopolitan
project. Perini Building Company is a wholly owned subsidiary of the
113 year-old Perini Corporation.
“The Cosmopolitan is one of the largest
contracts that Perini has ever had. Our portion of the project is
approximately $1.9 billion.”
As the real estate value on the strip
climbs and building sites become more scarce, developers are digging
deeper and building higher, and the Cosmopolitan is going where no
other building in Vegas has gone – five stories below the surface.
The Cosmopolitan is rising on the corner
of Las Vegas Boulevard and Harmon Avenue. The 8.5-acre site is
bordered by the Bellagio to the north, the new City Center project
to the south, and is built around the ’70s-era Jockey Club, which
sits almost in the middle of the construction site, says DeWees.
The facility will be a full-service
casino resort in a mixed-use, high-rise development that will
feature:
-
two 52-story towers
-
140,000 sq. ft. of
ballroom, convention and conference space
-
80,000 sq. ft. of
gaming and casinos
-
265,000 sq. ft. of
shopping and dining
-
44,000 sq. ft. of
luxury spa area
-
22,000 sq. ft. of
nightclub and ultra lounge overlooking the Strip
-
three wedding
chapels
-
a five-acre outdoor
facility with various beaches, European-style bathing,
multi-level bungalows and cabanas
-
five-level
underground parking garage
2005 start date
Dewees started on the project in October 2005, when excavation of
the 8.5-acre site began. First, micropiles were placed throughout
the site to help support the steel box beams that primarily support
the superstructures of the two 52-story towers.
“The soil on the site is varied, ranging
from caliche to sand to clay and cement-type soils in the first 20',
and then varied soil types below that. With this varied soil, we had
to make sure it could support the buildings, so we drilled more than
3,000 holes from the Strip level to 150' deep. These holes were 8"
to 12" in diameter in which a 6"-diameter pipe and 2" rebar were
placed in the hole and filled with non-shrink grout. These
micropiles support the mats that will carry the weight of the
complex,” he says.
“Eighty percent of the micropiles were
put in place from the Strip level; the remaining 20 percent were
placed once the excavation was complete. An earthen ramp allowed
trucks to enter the excavation, and once the soil was removed, we
had to place the micropiles in areas where the ramp was located,” he
says.
Once the micropiles were placed, crews
began excavating the site to 65' deep, which required removing more
than 900,000 cu. yd. of soil.
“There is an underground river that
flows through the site, so starting at between 16' and 20' down, we
encountered groundwater. As the ‘bathtub’ excavation continued, we
built a slurry wall that was first held in place by tiebacks every
10' that go back into the soil 65'. Also, metal decking will tie the
slurry wall to the box columns that also support the building. These
are placed on 30' centers,” he says.
“The slurry wall is the first of its
kind in Las Vegas,” says DeWees. “This is the type of construction
you’ll see in bigger cities where the space for the building
footprint is precious. With the five floors of underground space,
the Cosmopolitan will have nearly 40 acres of parking and holding
areas.”
Soil from the excavation was relocated
to a closed aggregate pit, which took an hour for each round trip.
However, during the excavation, that site was no longer available,
so the new location was a 1.5-hour round trip from the site.
The permanent dewatering system is the
first of its kind in Las Vegas, where sloped corrugated pipe that’s
covered with porous plastic cloth is covered with pea gravel. The
corrugated pipe drains the water into sumps where it is pumped into
the storm sewer and eventually finds its way back to Lake Mead. “The
water is tested to assure it’s not contaminated and the tests show
this water is extremely clean,” he says.
Once the excavation was complete, box
column construction began. “The box columns are between 2"- and
4"-thick steel and are 3' or 4' square or rectangle columns that
weigh 2,000 lbs. per lin. ft. It takes 48 hours of continuous
welding to join two sections of box columns together. Once they are
assembled, they are filled with concrete. We started them first
because they are a part of the critical path. Once they are
completed, the rest of the towers and buildings will tie into them
using conventional steel construction,” DeWees explains.
Jobsite logistics
With City Center, the largest privately funded construction project
in the country, going up adjacent to the Cosmopolitan and the
property being hemmed in by developed properties around it, lay-down
and delivery areas are tight and few. While Harmon Avenue is closed
for both construction projects, Las Vegas Blvd. can’t be closed.
To expedite deliveries, Perini has
modified the building process to increase lay-down and delivery
areas and carefully stages incoming loads so materials come off
trucks on a just-in-time basis so they can be installed practically
as they are unloaded. Loads carrying 60 to 80 pieces of steel start
arriving at 5 a.m. to get ahead of the heavy traffic on the Strip.
“We even bus our employees in from
remote lots because there is no parking available here. We also
prefab the concrete forms offsite so they can be just put in place
when they get here,” DeWees adds.
“We had the southeast corner of the
parking garage at the Strip level to be over-designed to support the
weight of cement and delivery trucks. In the west tower, we are
leaving out some of the lower steel structure so we can actually
pull into the tower with trucks and move materials up the towers
with manlifts. Tower construction is a 24/7 operation and we plan to
have them completed in a year,” he says.
Of the 44,000 tons of steel on this
project, the box column steel comes from Japan and almost all of the
other structural steel comes from U.S. sources. It’s first delivered
to a 20-acre lay-down area about 20 miles away from the site. It’s
loaded onto trucks in the order that it will be needed for
construction so it can be delivered to the site, offloaded and
installed almost immediately.
“We are working on a five-day cycle per
floor. We can really pour a floor a week in each of the towers, so
the towers will be completed in one year,” he says.
“We are prefabbing much of the work in
the towers because of lack of space on the site. Mechanicals, fire
protection and even the cooling towers are being prefabbed offsite.
The exterior window walls are panelized and the layout of the hotel
and condos allows all of the pipe and wire to be precut and labeled
for installation. All the plumbing trees are prefabbed,” he adds.
Worker challenges
With the onslaught of commercial construction in Las Vegas, finding
labor has been less of a problem than DeWees or others expected.
“There were big projects announced in
Las Vegas at the same time and everyone thought there would be
problems getting material and manpower. We talked to the unions and
subcontractors, and luckily the labor shortage eased. Plumbers are
hard to come by, but we have worked closely with union halls all
along the West Coast and they are getting workers here. We are also
finding paper hangers in short supply,” observes DeWees. Crews are
working six-day weeks and some are on seven-day workweeks. “There is
a full-blown day shift and a partial night shift. There is always
something going on at the site,” he says.
As the lower floors’ structural steel
and decks are put in place, the site, which is about 35 percent
complete, is already receiving glass walls and decorative Sicilian
stone used throughout the towers. The facility will have 2,200
luxury condos starting at $1.6 million and 800 hotel rooms. The
condo space can be rolled into the hotel room pool and both will be
managed by Hyatt.
With a scheduled opening date of
January, 2009, DeWees and Perini remain on track. “We’re getting the
exterior glass from China, and it comes to us in containers in order
ready to install. The stone and glass curtain walls are starting to
onsite now. It appears we will remain on schedule,” DeWees
concludes.
Published
in the March/April 2008 issue of
Contractor Tools and Supplies
magazine.
back
to top
|