|
All
aboard!
Las Vegas Monorail Project
Set
to open in 2004, this privately funded, non-profit project will
connect almost 25,000 hotel rooms and 4.4 million sq. ft. of
convention space with nearly four miles of fast, clean and efficient
transportation.
by Clair
Urbain
Building
an elevated monorail line anywhere is difficult, but constructing
one in a city that never goes to sleep and won’t tolerate business
disruptions makes the Las Vegas Monorail project extremely daunting.
“This
is the first monorail our company has ever done,” says Andy
Sorensen, field engineer for Granite Construction Company, which has
had extensive experience in building highways, dams, and bridges.
“All components must fit exactly. We have a tolerance of only
+/-1/16” in 5'. Many of the components are prefabricated off-site
so measurements and processes must be perfect.”
The
project is divided into 21 segments made up of five to seven spans
of monorail beams. The first step requires coring column supports
which are 6' in diameter and 20' to 40' deep. They are cut with a
computer-controlled drill that returns the rig to the exact position
it started, allowing crews to change drilling tools without spending
extra time realigning the rig with the hole.
“We
often must use a coring barrel with 56 carbide teeth to cut through
the caliche,” says Sorensen. The drilling rig can exert more than
12,000 psi. Sometimes, the clay is so dense it gets jammed in the
drilling barrel and must be jack-hammered out with a hoe-ram.”
In
sandy soil, the crews use a 6’ auger to cut through the soil
profile. Typically, crews can complete one or two shafts per day,
depending on drilling conditions.
“Even
with underground utility locating services, it’s amazing what we
run into when we begin sinking the shafts. In the early days of Las
Vegas, they didn’t mark things very well,” Sorensen says.
Once
the shafts are drilled, crews drop in a prefabricated rebar cage,
pump out excess ground water, and pour the caisson.
“These
caissons must be placed exactly because the precast beams rest on
them and must be within tolerance so the monorail cars can ride on
them smoothly,” says Todd Walker with the Las Vegas Monorail
Project.
Precast
precision
Once
the caissons are poured, a guideway support system is built on top
of the caissons. No two columns or track supports are exactly alike.
Due to space constraints, some are designed as cantilevered columns;
some have a straddle-bent design that straddles the roadway; others
have a simpler hammer-head design. Depending on the design,
different concrete mixes are used. Track supports are then
post-tensioned to the engineering specification.
|

A variety of column designs are
needed to support the monorail to meet traffic, property line
and clearance issues.
|
All
monorail guideways are precast at a facility 10 miles north of Las
Vegas.
“Concrete
is the only material that can make these unique structural
shapes,” Sorensen says. “We have no shortage of aggregate around
here, and concrete offers a smoother riding surface when compared
with steel track.”
The
precast yard is in the middle of the desert. The yard has three jigs
that crews use to custom-bend the rebar for each guideway beam. Once
the rebar is in place, crews form up the beam, then pour concrete.
Engineers
discovered that the extreme highs and lows of desert temperatures
can cause the forms to expand and contract, affecting the tolerance
of the beams. To help minimize that, curing is closely monitored
with a computerized system that tracks concrete temperature and
sends signals to adjust the temperature of the forms.
“There
are four lengths of heating coil on each side of the form,”
Sorensen says. “The computer records bed temperatures throughout
the length and increases or decreases heat to maintain a constant
temperature throughout the concrete. It prints out a report after
the cure and even does self-diagnosis if something isn’t working
right. The test cylinders are also controlled by this system so they
cure under the same conditions as the beams. This really is very simple,
efficient and dependable.”
Making
the move
With
little room on the right-of-way to store the guideway sections and
with heavy Las Vegas traffic, crews usually must move the sections
into the construction zone only on early Sunday mornings.
“We
have six trailers with rear-steering axles, and we can move in about
12 each week before traffic gets too busy,” says Sorensen.
The
spans are from 60' to 119' long and are very asymmetrical, so
lifting each one is slightly different.
Once
unloaded, lifting clamps are placed on the beams and two cranes
hoist the spans in place.
“The
crane subcontractor works closely from the plans to figure out the
best crane locations to do the pick. He writes up a lift plan and
circulates a copy to everyone. Once the lifting clamps are in place,
the contractor does a short lift to assure the span can be lifted
accurately and safely. The clamps often have to be realigned to get
the balance correct. Each pick is a little different because each
beam is a little different. In some cases, it has led to
‘spontaneous engineering’ to attain the correct span
placement,” Sorensen says.
To
maintain the tight tolerance of the project, precast yard workers
survey off of a tower that sits on a thermally insulated shaft in
the ground.
“We
can get from 5/8" to 3/4" form movement from the sun. That
makes it hard to achieve our 1/16" tolerance in 5'
requirement.” Sorensen says.
Mules
aid construction
Almost
all of the construction work takes place on the elevated monorail
guideways, so workers must have effective fall protection.
|

Contractors have built
"mules" that ride the guideways, offering workers platforms
that allow them to work with less bending and reaching.
|
“We
require 100 percent tie-off where falls are a danger. However, some
contractors have simplified fall protection by building ‘mules’
that ride along the monorail guideways,” says Walker. “The mules
allow workers to stand up in a supported platform that rides on top
of the monorail guideways. It puts the work at the workers' chest
level instead of having them lean over the guideway.
It’s more comfortable and provides them with the fall protection
they need,” says Walker. “Some of the units are motorized, so
they can be easily moved along the guideway.”
Construction
hazards
People
and traffic are the greatest challenges to this construction
project, followed closely by rain.
“This
is a busy city and people are here to have a good time. They are
everywhere at all hours. We have to make sure that construction
areas are well-protected so visitors can’t get into the work
areas,” says Sorensen. That means better fencing and barriers, and
at times, a security team.
For
example, the monorail route runs along Paradise Road and Sands
Avenue. Although workers must use part of the roadway to build the
monorail guideway, traffic must still be able to flow. It often
means moving traffic barrels for peak travel times when people are
going to or from the convention center. To do this, it can take as
many as 70 man-hours. “The roads must stay open. The only time
they will close is for large span lifts, and those are planned to
take place early in the morning and to take as little time as
possible,” says Sorensen.
Rain
is also a problem. “When it rains here, it is quick and big and
can quickly fill excavations and ruin buildings opened up for
construction. We have people on rain watch 24 hours a day, and if it
looks like it’s going to rain, we move fast to set up teams that
can cover work, run pumps, man mops and control the damage,” says
Sorensen.
|
The story
behind the monorail
Within a four-mile corridor that stretches from the infamous
Vegas strip to the Las Vegas Convention Center, there are
nearly 25,000 hotel rooms and 4.4 million sq. ft. of
convention space in nine facilities, says Todd Walker of the
Las Vegas Monorail Project. More than 35 million visitors come
to Las Vegas annually, and projections show that number will
climb.
“We project
more than 55,000 riders a day and expect to move approximately
20 million passengers a year,” he says.
Today, waits
for cabs at the convention center can take as long as two
hours. “When the monorail is in operation, the ride will be
14.4 minutes, including all stops,” he adds.
First
private mass transit project
The monorail began in 1995 as a private project that connected
the MGM Grand and Bally’s hotels and casinos. It effectively
spanned the one-mile gap between the southside MGM Grand hotel
and casino with the Las Vegas Strip. It proved successful,
moving 6 million passengers a year. It was a good experiment
that helped prove the viability of a mass transit system and
will be incorporated into the new monorail system.
It also
helped business. “Bally’s saw revenues jump 10 to 15
percent from the increased foot traffic brought in by the
monorail. In 1997, the vision to create a connection from the
convention center on the northeast side of the Strip with the
one-mile monorail already in place started to take shape.
“This is a
privately funded, non-profit system and the first one of its
type and the first one that we hope can fully pay for itself.
Buses and other public transit systems tend to be subsidized
by as much as 60 percent,” he says.
The four-mile
mass-transit project is the first of three phases. The second
phase will add monorail service from the Sahara Hotel to
downtown Las Vegas; the third phase will connect the airport
with the southernmost point of the monorail at the MGM Grand.
“Although
the first phase is totally funded by private sources, the
second and third phases will take advantage of federal
transportation funds and revenue bonds,” Walker says.
In the first
phase, many parties have a financial stake. In addition to the
conventional investors, hotels along the route were required
to commit $5 million of unsecured debt to the project and
grant right-of-way for the line. They also must pay for the
walkway or bridge that connects the hotel to the monorail
station.
Contractors
on the job also have a financial stake. Bombardier, the
company building the monorail cars and support equipment to
operate the driverless trains, brings $15 million in unsecured
debt to the project; the general contractor, Granite
Construction, carries $3.5 million in unsecured debt.
“This
is a 40-month, design-build project. If the monorail opens
sooner, Bombardier and Granite Construction get a portion of
the sales between when it opens and the scheduled open date;
if they don’t open on time, they will be assessed 1.1 times
the debt service cost until it opens. We are definitely on
schedule,” Walker says. |
|
More
about the monorail
The Bombardier Mark VI monorail cars are an advanced design
with roots in the monorail system used at Disney World.
“The
monorail style was chosen because it is a dynamic,
sexy-looking style that operates quietly, which is important
because the units travel very closely to hotel rooms,” says
Todd Walker of the Las Vegas Monorail system.
The
driverless four-vehicle cars can carry 225 persons, but
planning for growth, the stations and guideways are designed
to handle up to eight-car units. The units are powered by a
750-volt DC system and have a top speed of 50 mph. Five
traction stations, which are transformer stations placed along
the line, transform 12.5 KVA to 750 volt DC power. All
stations and trains are controlled by two operators on duty in
the Operations, Maintenance and Storage Facility (OMSF) which
sits at the end of the line near the convention center.
“The
traction station in the OMSF was built on-site, but the other
traction stations were prefabricated at the Bombardier plant,
then shipped in two pieces to the job,” says Reg Brockway,
Bombardier’s testing and commissioning manager for the
project.
“The
prefabricated units are great because they are fully
factory-tested. All we need to do is make a connection that
completes 200 connections we would have to otherwise do by
hand,” he says. Each traction station is also set up for
fast connection to a portable gen set if the system ever loses
utility power. Further, the stations offer redundancy to one
another along the line.
|

Prefabricated traction
houses are factory tested, then moved on site.
Connection is simple: One connection joins more than 200
circuits.
|
The
system will run from 6 a.m to 2 a.m., with four hours for
system maintenance. Under a series of contracts that spans 15
years, Bombardier will handle maintenance and operation of the
facility. |
Published
in the May/June 2003 issue of Contractor Tools and Supplies
magazine.
back
to top
|