|
Beating
the odds
Making
bids with incomplete information sounds like a gamble. Terry's
Electric Inc. improved its odds with good planning and experience,
helping it win the electrical work at the new Seminole Hard Rock
Hotel and Casino.
by
Clair Urbain
When
Terry’s Electric Incorporated (TEI) built its guaranteed maximum
price bid for electrical work on the Seminole Hard Rock Hotel and
Casino in Tampa, Florida, its attention to detail landed it the
biggest commercial job it has ever won. That fastidiousness is
keeping the job in the black, despite the “design as you go”
philosophy of the work and extremely tight completion deadline.
TEI,
which recently became part of the Xcelecom Company, is a $40 million
electrical contractor. Its founders, Terry and Jeanne Quigley,
started the family-operated company in 1979 with five employees. Its
commercial division has grown rapidly, completing about $25 million
per year in the growing Orlando/Kissimmee area. Industry watchers
report the company is the fifth largest electrical contractor in
Florida; the company has over 600 employees.
“This
is a $10 million-plus job, the largest single job we’ve ever
undertaken. It’s also the first casino job we’ve done. I think
we got the work because our attention to detail impressed Perini/Suitt,
the construction managers on the project,” says Stan Bunch,
vice-president of TEI’s commercial division.
Making
the numbers work
Behind
the walls of today’s casinos, an information superstructure keeps
tabs on customers, employees and equipment. From lighting systems to
slot machine activity, systems are in place to make the casino
environment as secure and as conducive to gambling as possible.
Although
the finished systems are complex, TEI estimators had little to go on
in the bid phase. They had to use some creative research to come up
with a realistic cost.
“We
pulled take-offs from electrical drawings, interior design sketches,
architectural drawings and exterior drawings. We had to combine
three lighting designs into one. None of them were complete. We had
four estimators work on this project nearly around the clock for two
weeks to come up with a bid we were comfortable with,” Bunch
recalls.
The
number the estimators came up with was considerably higher than
other bidders, but the thoroughness and attention to detail
impressed the general contractor. TEI got the job, which broke
ground in May 2002; the first phase, which includes building 40,000
sq. ft. of the 100,000 sq. ft. casino, Hard Rock Café and
back-of-house area, must be completed by April 2003. The second
phase, which has already started, includes building a 12-story,
four-star hotel. Once the first phase is completed, the casino will
move into the new building and continue operating while the old
casino is razed and the final 60,000 sq. ft. of the complex is
built. Target completion date is March 2004.
Most
TEI commercial division workers are long-time employees who live in
the Orlando/Kissimmee area near the home office. “We feel that
keeping electricians on the payroll for the long-term is good for
our business,” says Bunch. “We train them right from the start
and then continue developing their skills as time goes on. We
concentrate on safety, and it shows on this jobsite. We have had 152
days so far on this jobsite and they have been accident-free,” he
says,
Distance
a factor
Running
its biggest job ever in Tampa, when the home office is in Kissimmee,
nearly an hour away, presents some challenges, says Dennis Postler,
project manager. “There are about 35 TEI employees on this job who
live near Kissimmee. We run buses to the jobsite every day from
Kissimmee so workers don’t have to drive.”
The
job averages 40 electricians and six casual labor, but at its peak,
will have up to 80 electricians on the job. “We also have a
materials manager with three assistants, an assistant
superintendent, five foremen and four team leaders. This job isn’t
over-staffed, and with proper planning, we can get the work done.
On-site support staff include my assistant project manager, Dennis
Grenet, a full-time CAD operator and a full-time
office person,” says Postler.
To
prevent bottlenecks in the construction process, TEI works closely
with other subcontractors. “We look at the project schedule three
weeks in advance and make a plan on how to get the work done by that
date,” says Bunch.
At
weekly meetings with other contractors, TEI looks at their progress
and discusses ways to help them out. “For example, we were
starting to get behind installing cable trays. We worked closely
with the plumbing contractor, using our CAD diagrams to figure
elevations to assure there would be no conflicts. It worked well,”
Postler says.
The
on-site CAD operator has been key in getting the company on top of
the schedule and sticking to it.
Because
much of the design is work in progress, TEI workers flesh out
what’s needed, then the CAD operator produces drawings that can be
submitted for review and approval. Once approved, the team leaders
on the site use the color-coded CAD output to coordinate work.
It’s printed on standard letter-sized paper for easy use by the
installers.
All
work is attached to a cost code on the job so TEI can accurately
track how long it has taken to complete a job vs. what has been
budgeted.
“We
have a very tight documentation process that helps us track
progress. It really helps eliminate loose ends at the end of a
project,” Postler says.
Because
of the extreme technical nature of the lighting, security and
information systems, TEI works closely with various specialty
subcontractors who are familiar with this type of work. Taking
advantage of their expertise helps reduce the odds of falling off
schedule or going over budget.
“It’s
important to get on a schedule and plan for the work, then follow up
with the other contractors to assure everyone is working
together,” says Daren McDermott, job superintendent. “We have
weekly meetings with the other subcontractors. We set forth from the
beginning what we will supply. It’s documented with the other
subcontractors. If they have a need, we refer to the document to see
if it’s covered. If it’s not, we discuss who is paying for what.
“For
example, it’s in our contract to maintain temporary electrical
service throughout the construction phase. If a contractor wants
more power, we provide it. We also watch how they use the power and
make sure they are using it safely,” he says.
While
many electrical contractors rig up their own distribution panels,
McDermott says TEI prefers to use portable spider boxes for
temporary power distribution. “They cost more at the front end,
but they are sturdy and provide reliable power. We think they save
us money in the long run.”
The
50-amp spider boxes come with a 50' cord and twist-lock plug. The
units can supply 220-volt or 110-volt power and have self-contained
GFCI breakers. An end receptacle allows another spider box to be
plugged into it, creating another 50' run of power.
“They
are easy to test. We test them weekly to make sure the GFCI is
working correctly. We record the test on a sticker on the top of the
unit,” he adds.
The
model room
Due
to the design-as-you-go process of construction, the general
contractor has built full-size models of a portion of the gaming
area and of the hotel’s guest rooms. The mock-ups help finalize
design before construction proceeds too far.
“The
life-size mock-up of the hotel rooms has been very helpful,” says
Postler. “Initially, they wanted all the outlets easily
accessible, but once they saw what it looked like, they decided to
drop them behind the furniture. The headboards, which have a light
integrated into the side tables, look sharp, but will come with a
pre-cut hole in them for the light to pop through. That means we
have to be very exact when we wire in the power for those lights. By
having this mock-up, we can make the exact measurements and then
install the power so it matches up exactly with the headboard.”
The
model room also helps the crews to install room wiring quickly.
“We are prefabricating the wiring off-site. We take exact
measurements, then the CAD operator develops a plan that assembly
crews at our mechanical facility can build,” he says.
Each
component is labeled with a self-stick tag and palleted with the
other electrical components for each room. “The CAD drawings allow
us to easily flip the design over because the rooms next to each
other are mirror images. We think prefabricating assemblies cuts at
least 30 percent of the cost out of the job. The crews can really
fly,” he says.
The
crews also use prefab assemblies for PVC conduit runs. “We have
well over 100,000 linear ft. of conduit in the ground. We
prefabricated every 90-degree bend on site with a hot box,” says
McDermott, saving substantial time and money when compared with
installing a 90-degree elbow.
Simplified
supply
Getting
supplies and keeping track of them on fast-track projects can become
an extreme challenge. To simplify the process, TEI uses a
consignment system with select distributors. “We have them give us
prices on the whole job of the common things we need, then we have
them stock on-site trailers with a more than ample supply,” says
Bunch.
Daily,
the jobsite foremen or team leaders assemble a supply list of what
they will need for the next day and turn them in to Don Levasseur,
the materials manager. He enters the order on a personal digital
assistant (PDA) outfitted with a barcode scanner. He simply scans a
part number out of a directory, then enters quantities and cost
codes.
Once
a day, he synchronizes the PDA with the desktop computer in the
office. From there, the distributor can access the information for
billing and refilling the consignment inventory.
“This
is the fourth job where we have done this and we think it has cut
our material costs by 20 percent. Plus, I don’t have to worry
about getting the supply requests in for the day-to-day supplies.
It’s already here, and we don’t pay for it until Don scans the
order,” Daren says.
Inventory
levels are tracked by the distributor. Typically, there is enough
inventory to last about two weeks.
For
Levasseur, the system works well. “It takes much of the guesswork
out of keeping supplies on hand. It takes tons of paperwork out of
the system,” he says.
|
Training
for long-term employment
“When we look at jobsite injury statistics, workers who have
been on the jobsite for less than a year are the most likley
to be involved in an accident,” says Daren McDermott, TEI
jobsite superintendent. “That’s why we take new worker
training very seriously.”
Employee
turnover at TEI is practically non-existent, and McDermott and
his associates believe that TEI’s comprehensive training
programs are mainly responsible for that.
Before
a new employee starts on a jobsite, he or she goes through a
three-phase safety program. The first step involves a
three-hour meeting where all of TEI’s safety policies are
explained, then each new employee gets a TEI safety manual.
Next,
the employee goes through a 1.5-hour Owner Certified Insurance
Program that covers other safety information in detail,
followed by a walkaround on the jobsite that covers specific
hazards on the site as well as the following points:
1.)
Review of safety manual
• Explain company safety policy
• Explain safety rules
2.)
Emergency preparedness and disaster training
• First aid procedures
• Emergency signs
• Reporting, evacuation procedures
• Pregnant women (if applicable)
3.)
Lockout/tagout
4.)
Fire extinguisher location and use
5.)
Trenching safety
6.)
Electrical safety/assured grounding program
7.)
Personal protection equipment
• Hard hat (required)
• Safety glasses (required)
• Hand protection (gloves, etc.)
• Welding (Hood, glasses, etc.)
• Hearing protection (when required)
• Dual eye protection for grinding
• Fall protection (lanyards, harnesses, etc.)
• Respiratory protection
8.)
Vehicles
• Parking, mandatory proof of insurance
• Company equipment
• Speed limits
• Seat belt use (mandatory in company vehicles and
equipment)
9.)
Housekeeping
10.)
Other safety practices
• Smoking policy
• Equipment operation
• Forklift safety
• Lifting practices
11.)
Report unsafe conditions and acts (including workplace threats
and intimidation)
12.)
Confined space entry
13.)
Locations of first aid kits
14.)
Importance of attending weekly safety meetings
15.)
Hazard communication program (location and use of Material
Safety Data Sheets)
16.)
Company disciplinary procedure
Once
the supervisor covers the points on this checklist, the new
employee and the supervisor sign the form. “This form must
be turned in before the employee starts on the job,”
McDermott says.
All
employees are certified for scissor-lift operation, and
appropriate personnel receive backhoe loader training and
certification. “We match the added training to the
workers’ specific jobs,” he says. All foremen are
certified in the OSHA 10-hour training, have CDL licenses, are
trained in CPR and how to handle blood-borne pathogens. “The
training seems to be never-ending, but it is important,” he
adds.
Weekly
safety meetings
In addition to the thorough training at the beginning of
employment, TEI backs it up with weekly safety meetings on the
jobsite. “They are completed by one of our three full-time
safety directors who also does a complete site inspection,”
says McDermott.
If
a worker disobeys any safety rule, the safety director or
supervisor will issue a verbal warning. If the worker is cited
more than once for the violation, the safety director can
issue a written citation that goes in the employee’s
personnel file or can immediately remove the worker from the
site.
Daily
inspections
Workers inspect the tools they use daily for wear or damage;
power cords are checked once a week for nicks, cuts or wear.
Equipment operators complete a checklist before operating
equipment. Any maintenance issues are directed to the
maintenance department. |
Published
in the March/April 2003 issue of Contractor Tools and Supplies
magazine.
back
to top
|