|
Bridging
greatness
Work begins on the Colorado River Bridge, the longest arch span in
the U.S. and the fourth longest in the world that’s part of the $234
million Hoover Dam Bypass project.
by
Clair D. Urbain
Visitors to the Hoover Dam still marvel at the engineering and
construction feats that it took to build this superstructure 70
years ago. Today, another engineering and construction marvel is
under construction just 1,600' to the south of the dam – the Hoover
Dam Bypass. When finished in 2008, it will feature four miles of
four-lane highway that takes a straight shot across the mighty
Colorado River with a nearly 2,000' long bridge supported by the
longest arch in North America.
Burgeoning growth in the Las Vegas area and traffic congestion makes
travel on Highway 93 a slow and, in some ways, dangerous drive
across the Hoover Dam and the Nevada-Arizona state line.
Heavy
traffic on the narrow, two-lane road with several switchbacks does
not mix well with the mass of tourists visiting the dam.
Highway 93 is also designated as a North American Free Trade
Agreement (NAFTA) route, so the congestion and security issues were
no longer acceptable.
To
alleviate the traffic and improve safety, the Central Federal Lands
Division of Federal Highways is the lead agency responsible for
management and delivery of the project. It is coordinating the
efforts of Federal Highway Administration (FHWA), the states of
Arizona and Nevada, the Bureau of Reclamation, the Western Area
Power Administration and the National Park Service on this
three-section project to build the bypass.
The
Arizona and Nevada approach projects, which total $51.6 million, are
complete and in February 2005, work began on the Colorado River
Bridge, the longest concrete arch bridge in North America and the
fourth longest in the world.
The
88'-wide, four-lane bridge with pedestrian crossing will tie the
completed approaches together. This engineering wonder is
aesthetically pleasing and combines several building technologies to
achieve a cost-effective and well-engineered solution to traffic
problems.
General contract work for the bridge is under the control of a joint
venture between Obayashi and PSM Construction USA. Obayashi is known
for its tunnel and bridge work around the world, completing projects
in Atlanta, Seattle and portions of the Big Dig in Boston. PSM
Construction USA is known for its pre-stressed concrete construction
experience, says Mike Motil, Colorado River Bridge project manager.
“This
is a challenging job. There was nothing here one year ago and since
then, subcontractor Ladd and Associates has been blasting and
removing rock for the bridge foundation and abutments. This is a $15
million subcontract out of the $114 million bridge project. They
have done an excellent job of safely and efficiently removing
640,000 cu. yd. of rock to make room for the columns and abutments
that will support the bridge,” he says.
Environmental concerns
Protecting the environment is
a high priority on the project. From landscape to wildlife, careful
monitoring assures that work isn’t adversely affecting the area.
“Before we started removing rock from the canyon walls to make room
for bridge foundations, we monitored normal vibration in the area
for one month to establish a baseline. The 26 seismometers are still
in place, monitoring vibration from construction. They are
positioned 110' left and right of the bridge centerline on each
substructure unit. This is fractured rock, which means blast effects
can be unpredictable. Because of this, crews have been using small
charges to remove rock,” says Motil.
To
prevent rock from falling into the river, crews install extensive
rock containment systems before removing any material. Once rock is
removed in some areas, rock bolts are inserted back into the
mountain to stabilize the remaining rock.
One of
the largest herds of desert bighorn sheep in the United States
reside in the area, and the spec requires they aren’t disturbed or
displaced by the project. Field supervisors report sheep sightings
so they can be tracked and to assure work doesn’t affect their
habitat.
Barriers have also been built around the jobsite perimeter to
prevent tortoises and other wildlife from entering the finished
roadway. Both approaches are designed with wildlife crossings so
animals can cross under the bypass to reduce chances of being hit by
motorists.
To
minimize site contamination, the contractor uses a 100 percent
biodegradable bond breaker on forms used for column construction.
Bridge construction
Designers chose a composite
concrete deck arch design for the bridge, which will cross Black
Canyon about 1,600' south of the Hoover Dam. This design addresses
cost, schedule, aesthetics and technical excellence required to meet
the demands on the site, says Motil. “The concrete composite
alternative blends the best of concrete and steel, using compressed
concrete for the arch and lighter steel for the upper structure,” he
says. The bridge decking will be cast in place.
This
bridge will be the fourth largest arch in the world and will rise
900' above the river. Its cast-in-place concrete arch will be built
using custom form travelers built by NRS in China. “This design also
allows work to simultaneously take place on-site during arch
erection and in the shop for superstructure steel fabrication,” he
says.
To
build the span, Motil’s crews will use twin 50-ton luffing highline
cable cranes specially designed for this job. “The cable way is
anchored into solid rock. It will be used to build the foundations,
place the bridge columns, erect the tub girders and then service the
four form travelers that will be used to build the arch,” he says.
After the arch is built, the cranes will place the spandrel columns,
tub girders and then place the bridge deck.
The
twin towers have heavy 3"-diameter lines that run across the canyon.
The luffing crane design allows the highline to move from side to
side to maneuver the wide variety of building materials into the
canyon.
Designing the luffing crane towers was challenging because the road
comes in from the right and the bridge turns left as it crosses
Black Canyon. “There was little space in which to anchor the cranes.
We are anchoring off the mountain on both sides,” he says.
Preliminary foundation work continues with two other cranes
positioned on each side of the river. “Ladd and Associates is
subcontracting this work. They are blasting fractured rock, which
can be difficult to control. There is a chance a blast will take out
too much or not remove anything at all, but what’s left gives you a
solid foundation.
“There
are power lines all around the cranes. There is a 230 KV line on the
Arizona side and a 2.3 KV line on the Nevada side. We have the
cranes configured so they can’t turn into the power lines,” he says.
Before construction could begin on the approach contracts, several
transmission lines had to be relocated and upgraded to make room.
Most
concrete will be poured at night. “The temperatures here can reach
120 F and winds can reach 100 mph. Our equipment is engineered so
that we stop work when the winds reach 30 mph and must lash down the
towers in 50+/- mph winds. The FHWA supplied five years of wind
data to help engineer the construction,” he says.
While
this is a big job, there is room for only about 100 workers on the
site. “This is like doing a $25 million job four years in a row.
There is not much in each foundation or traveler, so we have many
smaller crews,” Motil says.
Many
of the workers are at the pre-cast site at this time, building the
column sections. “As columns begin to be transported to the site and
placed, some workers will move from the pre-cast yard to the bridge
site. In both locations, we demand 100 percent fall protection on
the job, whether they are working 6' off the ground or 900' over the
Colorado River,” he says.
Column construction offsite
“The support columns rising
from the canyon walls must be constructed with extreme accuracy.
Their design is also aesthetically pleasing,” Motil says.
In
total, the project requires 440 pre-cast concrete pier segments and
64 concrete pylons. The columns are engineered to slightly taper as
they are stacked on one another. They are built sequentially in the
pre-cast yard, one on top of the previous one, to assure a perfect
fit. Each piece is numbered and matched perfectly so they can
transported, placed and then doweled together on-site.
“At
the pre-cast yard, we are building two to three column segments a
day. We are working ahead because when we begin placing them, we
hope to place four to six sections each day,” he says. Each column
segment weighs as much as 40 tons and each pour is approximately 15
cu. yd. Every concrete load is checked for slump and other
performance factors.
The
pre-cast yard has three forming/pouring areas. Two are for regular
column segments and the third is for the top or base segments and
the pylons. “We always pour on top of the previous column segment
and move in a figure 8 fashion. In the curing area, up to 14
segments are held for seven days and watered to allow for an even
cure. The segments are moved around the yard with a 50-ton mobile
crane.
In one
area of the yard, crews use a template to build the rebar structure
for column segments. They place forms precisely, guided by geometric
controls that are checked for accuracy every day at 2 a.m. Once
they’re checked, the forms are repositioned for another pour,
working off the previous day’s segment.
The
column segments are made with 6,000 psi concrete; the arch will be
made of 10,000 psi concrete and the foundations are 4,000 psi
concrete.
Once
the column segments are set in place, they will be joined with a
10'-long bar that will be slipped in from the top of a column
segment and bolted to the segment below.
“This
is an engineering feat and we have great engineers who are planning
it,” Motil says.
While
building the arch, a temporary cable stay system, much like what’s
used on suspension bridges, will support the arch and traveling
forms. Once the arches are completed, the cable stays will be
removed and the arches will be freestanding. Then, the precast
columns will be installed vertically on the arch.
Steel
tub girder construction requires a special certification for
installation. “That will be handled by Utah-based steel construction
contractor OlsenBeal,” says Motil.
Watch the progress
To watch progress on this
project, go to
www.hooverdambypass.org. There, two Web cams monitor the site.
It also features project images and a virtual bypass drive-through
that shows how much earth was moved to create this project.
|
Bridge
approaches move mountains
The country that
surrounds Hoover Dam and Lake Mead is rough, and
straightening and leveling roads is no small feat.
Combine that with power lines
snaking through canyons, infrastructure already in place
serving the Hoover Dam area and strict environmental
guidelines to protect habitat for native species, and the
word rough takes on a whole new meaning on the approach
projects.
The Arizona and Nevada
approaches to the Colorado River Bridge required extensive
blasting, filling and reinforcement to establish a
21st-century roadbed for the Highway 93 Hoover Dam Bypass.
Careful planning minimized the
new road’s effect on moving power lines and disturbing
habitat.
Contractor Edward Kraemer & Sons
was responsible for the Nevada Approach project. The $30.1
million project is a 2.2-mile, four-lane roadway that
required construction of six new bridges and 1.6 million cu.
yd. of earthwork. More than 50,000 sq. ft. of retaining
walls were installed.
The Arizona Approach project
consists of 1.8 miles of four-lane road that was built by a
joint venture between R.E. Monks Company and Vastco Inc.
The contractors constructed the
two roadway, including the 900' bridge that spans a canyon
just east of Sugar Loaf Mountain.
Both projects included creating
nine wildlife crossing areas, drainage improvements,
extensions to National Park Service trails and trail access
parking. The projects tie the bypass to the existing Highway
93.
To maintain the scenic profile of the area,
the contractors stained newly exposed rock cuts as directed
by the Design Advisory Panel on the project. |
Published
in the March/April 2006 issue of Contractor Tools and Supplies
magazine.
back
to top
|