|
Building
around tradition
Building
a 21st century world class art center in the middle of a 19th
century Southern-style neighborhood means looking at construction in
some very non-traditional ways.
by Clair
Urbain
The
rich architectural tradition in Savannah, Georgia, makes this city
unique. Built when cotton was king in the Delta, the city works hard
to maintain the flavor of the 18th and 19th century buildings while
adapting them to the 21st century world.
When
the Telfair Museum of Art proposed building the 64,000 sq. ft., $26
million Jepson Center for the Arts in the heart of Savannah’s
historic district, it met with some critical eyes from the Historic
Review Board, which is charged with maintaining the look and feel of
Savannah.
After
several design changes and fastidious attention to detail that
allows the facility to attract world-class exhibits, the plan on
paper can best be described as complicated.
That’s
the first word out of the mouth of the project’s general
contractor Walter B. Murphy III, president of Rives E. Worrell Co.,
Inc., as he describes the project. As general contractor, Murphy’s
company handles the concrete and carpentry work and coordinates
other work with subcontractors he hand picked for this high profile
job. The building, approximately 20 percent complete, will open in
early 2005.
“This
is one of the most complicated buildings ever built in the Savannah
area. It has many geometric curves in the design and has over $2.5
million of glass in the walls and the roof. It’s actually two
buildings that are connected by a bridge that spans a lane,” he
says.
World-renowned
architect Moshe Safdie and Associates designed the museum, adapting
original plans to answer the review board’s objections. While
blending into the city’s historic urban architecture, it features
vast open areas that rely on light and shade to create an
interesting environment for exhibits. Cream-colored Portuguese
limestone and architectural concrete help tie the building in with
Telfair Square and neighboring 19th century buildings. The facility
has gallery space, two auditoriums, educational galleries, offices,
a library, sculpture gardens, a museum shop and a café.
Complex
construction
The
curved, skewed walls and exceptional use of glass in walls and
skylights presents interesting challenges to builders.
“The
two buildings start at different elevations. There is a 2' 8"
difference in elevations, but the coursework of the walls must line
up and finish at the same height,” explains Murphy. “Because of
the curves in the design, there are some very large radii that make
construction difficult. Up, down and all-around, we must be sure we
are exact.”
To
assure accuracy, site engineers established several control points
on the site. A reference point across the street on Telfair Square
also helps double-check all measurements.
The
structural steel, immense by most building standards, carries the
spans needed to create an open, flowing environment. The three-story
buildings will have concrete floors; walls will be windows or
limestone veneer on concrete.
“The
limestone will be quarried in Portugal, cut in Italy and loaded onto
cargo containers that will be delivered to the Port of Savannah. The
Italian stone cutter is only one of three companies in the world
that can cut the limestone to the specs we need,” says Murphy.
Once
the structural steel and concrete floors are in place on each floor,
Harold Swailes, the project superintendent, will use templates made
from 3/4" plywood to maintain layout accuracy.
“I
went to a large parking lot and laid out the radius curves onto
plywood. The longest template was 190'. There are many different
radius walls coming together in this design. The roof has a 221'
radius; another radius is 199', which becomes a 105' compound radius
that meets up with another that is 65'. To further complicate the
building layout, the inside wall of the three-story main lobby skews
inward.
“If
we didn’t use a template, we would be measuring all day. The
template is the best way to physically do it and keep it
accurate,” Swailes says.
The
architectural concrete used on the façade entrances offered Swailes
and his crew some challenges. “It’s all cast-in-place and has no
forming penetrations in it. It’s a totally different forming
system from what we use in conventional concrete work. The concrete
is also five times as expensive, so it takes some attention to make
sure it comes out right,” Swailes says.
To
achieve the smooth, penetration-free face, the forms are made of
Finn-form plywood that is smooth on the inside and coated with a
release agent. All corners have gaskets that seal the form, and
2" x 8" whalers clamped around the form hold it in place.
Once poured, the concrete is vibrated extensively for a smooth
finish.
The
design calls for a joint line every 4' in the wall face that will
align with the stone courses. To accomplish that, Swailes and his
crew used 4' x 4' plywood sheets separated by a working joint to
create a mortar-joint effect. “The concrete consultant checked out
the work and says it is some of the best architectural concrete that
he has seen in this country,” Swailes says.
Space
challenges
The
building’s open, airy design provides little space for mechanicals
and strict fire protection requirements makes this one of the most
unique and challenging projects that Everette I. Boaen, president of
Boaen Mechanical Contractor, Inc. and his crews have ever worked on.
“We
are in charge of the HVAC portion of this job. It’s a $1.6 million
job that uses some very interesting methods for fire control and air
movement,” Boaen says.
Sultry
Savannah weather makes temperature and humidity control critical,
says Boaen. “There is triple-redundancy on all controls. The
museum requires that humidity be controlled to 55 percent, plus or
minus five percent at all times. The system used in this building is
the same design used by the Peabody Museum in Philadelphia and the
Smithsonian Institute.”
Fire
control systems are also complex. Because sprinkler systems could
damage artwork, the museum is outfitted with a dry fire-suppression
system.
To
control smoke damage, the building is designed to be
super-ventilated during a fire. “The dry fire suppression system
will put out the fire, but the positive ventilation system will get
the smoke out quickly,” Boaen says.
“In
other buildings, fire dampers shut down air flow in the HVAC system
if there is a fire,” says Ed Shuman, Boaen’s on-site project
superintendent. “In a fire, this system shuts down the HVAC system
and uses two high-cfm fans to move air through the HVAC ductwork and
into the building. Then, 11 exhaust fans installed in the roof
quickly pull the smoke out of the building.”
The
ductwork, made with heavy-gauge metal, is insulated with two layers
of fire wrap that offer 2,000 F protection for two hours. “This is
the same material used for zero-clearance exhaust hoods. It’s very
expensive, but allows us to meet the zero clearances needed in the
building’s design,” says Shuman.
To
maintain the open design of the building, ductwork often penetrates
the structural steel. “The structural steel is prefabbed with duct
and other openings in place. We build all of our duct work and
connections off-site based on the engineering drawings, and in the
case of the mechanical room, they gave us an allotted amount of
space and told us to figure it out. In many ways, this is a
design-build type of job for us,” says Shuman.
“We
have been prefabbing most of our piping work off-site for several
years now,” says Boaen. “At first, some of the workers didn’t
think it was possible, but when we were able to set air handlers and
pumps in two or three hours instead of two or three days, they
became believers in prefabbing piping off-site.”
“Space
on the jobsite is very tight,” adds Shuman, “Prefabbing makes
the most sense here. We don’t have room for a jobsite trailer,
much less any room for a fabrication area.”
Trades
work together
The
buildings’ designs leave little room for any trade to make a
mistake, so the trades must work together to get the job done.
Although
it can be a challenge, Shuman says the continuous contact with other
subs and the general on the job has prevented problems.
“I
produce the shop drawing and share it with the other contractors. We
discuss where we have problems and solve them before they happen. We
double-check each other’s work and formally meet every two weeks
on the project on concerns. We have very good communication among
all of the trades.”
Even
with the complexity of the project, Murphy is pleased with the
progress. “This is a high-profile job and the job is going well
because contractors working on it were chosen because of their
reputations. The high quality of subs on the job and their
workforces are paying close attention to what they are doing. Many
times, workers don’t take an interest in what they are doing.
That’s not how these guys approach their work, and it shows,” he
concludes.
Published
in the July/August 2003 issue of Contractor Tools and Supplies
magazine.
back
to top
|