|
Combining
the old with the new
By
Clair Urbain
How
Gibbs Construction is changing the face of New Orleans’ French
Quarter . . . without changing its look.
The
French Quarter in New Orleans has one of the most distinctive
personalities of any neighborhood in the United States. Steeped in
tradition and trademarked by centuries-old architecture, the keepers
of the city’s culture aim to preserve its look and feel yet allow
the city to revitalize its downtown area.
Host
of Super Bowl XXXVI and international trade shows that draw tens of
thousands of visitors to the city, hotel space is at a premium.
Developers must work closely with the Vieux Carré (pronounced voo
ca-ray) Commission to assure any development does not detract from
the quaint, distinctive look of this historic district. Strict rules
govern renovation and replacement efforts.
Gibbs
Construction, a design-build commercial contractor with deep roots
in the New Orleans area, is working closely with developers,
architects and the Vieux Carré Commission to add more than 700
rooms to the city’s hotel capacity.
The
fast-track $60 million Bourbon and Canal Hotel project, owned by the
Decatur Hotel Corporation, is transforming the very northwest corner
of the French Quarter into two hotel properties. The 512-room Astor
Crown Plaza features ballrooms, meeting rooms, restaurant and
convention facilities and
recreational areas. The Alexa, a four-star, 192-room boutique hotel
that adjoins the Astor, features upscale accommodations. Both
properties literally envelop centuries-old buildings, preserved for
their architectural style.
Gibbs
Construction is no stranger to renovation work, says Melissa Gibbs,
who helps her father, Lawrence, the company founder and president,
operate the commercial contracting firm. “My father started this
business in a spare bedroom in our home 25 years ago with $3,000.
The company has grown from there to $120 million in revenue in
2001,” she says. Many of their projects have been in the French
Quarter and in otherhistoric
areas of the city.
The
firm employs about 260 full-time people. It completes most layout
and rough vertical forming work, followed up by finish work at the
end of the project. “We look at the job, then match the best labor
to the job. That could be our own people or subcontractors we work
with,” she says.
Special
challenges
Working
in the French Quarter presents special challenges. Once the design
and engineering work passes the muster of the Vieux Carré
Commission, working around centuries-old buildings in tight quarters
can make even easy jobs difficult.
To
maintain the look and feel of the French Quarter, several buildings
around the hotel complex were saved. Although the Woolworth store on
the site was demolished, the façade of the Imperial Shoe Store
building at the corner of Canal and Bourbon Streets, as well as the
first floor of a variety of buildings on Canal Street, had to be
saved. Businesses in many of those buildings stayed open throughout
the construction process, requiring Gibbs to work closely with them
to maintain dry space as construction continued above them, says
Danny Femal, senior superintendent on the jobsite.
“We
started demolition of the old Woolworth building right after Mardi
Gras in 2001,” says Femal. “We had an eight-day turnaround to
get the foundation in for the 16-floor section of the Astor hotel
because it involved working around a Krystal’s restaurant on the
jobsite. This section of the hotel was literally built over the
restaurant, with a steel structure bearing the weight of the hotel
over the top of it,” he says.
From
day one, work space on the site has been tight. “We have only 100'
of access on the front and back of the site. On the front, it was
only 20' wide, and on the back, it was 12' wide. This building was
built on the sidewalk,” he says. Using Primavera job-scheduling
software, the construction team coordinated deliveries to assure
supplies would be on time as workers needed them.
“We
found that no matter what time of day it is in the French Quarter,
you have crowds and at some times of the day they are harder to deal
with. We found that 4 a.m. was the time to start pouring
concrete,” he says. Gibbs hired off-duty New Orleans police plus
three traffic coordinators to maintain traffic flow.
With
a tight jobsite, the Gibbs team needed to find a way to get concrete
where it was needed on the construction site. A hardline and spider
combination commonly used for larger pours was impractical. A crane
and bucket was first used to pour small mezzanine jobs, but wasn’t
fast enough. “Instead, we used a crane and placing boom to pump
concrete for high-volume pours,” says Femal.
Working
with Cajun Concrete Services, the local concrete pumping company,
workers used a 36-meter detachable boom that could be mounted on one
of two towers on the site. “We were able to get 75 to 80 cu. yds.
poured per hour and poured 14,000 sq. ft. per week at the beginning
of the project. When we reached the eighth level, the floors were
more typical, so we achieved 20,000 sq. ft. per week from that point
on” he says.
The
detachable boom allowed the pump truck to be positioned in the tight
quarters below, then pumped the mix up to the work level. From
there, workers used a remote control to position the boom and make
the pour.
“We
would pour the slab in the morning and the columns in the afternoon.
Decking would be placed and six days later we would be ready to pour
the next floor,” he says.
Ballrooms
needed special concrete
Constructing
the ballroom in the middle of existing buildings required innovative
engineering that used post-tensioned concrete.
“The
ballrooms on the second level required clear spans, but had to
support a portion of the 16 floors of hotel rooms above the
ballrooms. “To accomplish that, we needed to build seven transfer
girders that are really 36" x 178" concrete beams,” says
Femal. “The post-tensioned beams are 75' long and made up of 130
cu. yds. of Agilia cement. This is a hydraulic concrete with
11.5" of slump. It is self-compacting and achieves 5,000 psi in
36 hours. We wanted concrete mix that would get strong fast because
we wanted to stress the cables as soon as possible so we could
remove the forms to reduce congestion on the jobsite,” Femal says.
“The Agilia cement is amazing. It solved our problems,” he adds.
Exterior
building challenges
Laying
brick to complete the new portion of the Astor Crown Plaza required
bricklayers to work from hydraulically powered scaffold jacks that
hung from the top of the building. “We had to stage the brick work
over the top of the present buildings. We thought it would affect
the bricklayers’ productivity, but it didn’t. The key was
keeping bricks and mortar fed to the layers,” he says.
On
sections of the buildings that had to blend in with adjacent
historic buildings, 1 1/2"-thick glass fiber-reinforced
concrete panels were used as cladding. “It’s a thin panel of
pre-cast concrete that is mounted to a steel frame. The forms can be
manipulated to match the decorative look of the area. It allows us
to build arches, round windows and other architectural designs
needed to blend in with the surrounding buildings,” he says.
Getting
more interior space
To
maximize the number of hotel rooms that could be built in the Alexa
hotel, building designers came up with a light well that cuts
through four of the old buildings facing Bourbon Street. Although
the first floor remained relatively untouched, workers cut out a
section of the roof and portions of the second through fourth floors
of these buildings to create a light well. This allowed interior
rooms to have exterior windows. On the back portion of these
buildings, two additional floors of hotel rooms were added. “We
were able to proceed with minimal water damage during
construction,” Femal says.
To
get ahead of finish work, Femal’s crews staged the job so work on
the Astor lobby could proceed ahead of other job segments.
“Keeping
that part of the building dry was a challenge because it is located
adjacent to the Imperial Shoe Store building. It is six stories
tall, and was completely gutted for renovation. We added 16 openings
in this six-story, load-bearing building without bringing the
building down,” he says.
“Finishing
the lobby while building construction continued helped assure us it
would be totally done for the “soft” opening scheduled for the
end of February, 2002 and grand opening the end of March,” he
says. These are key dates because that month of limited operation
will help us get the life and safety systems fully operational and
it will allow the staff to get familiar with how the building
operates,” he concludes.
Published in the
March/April 2002 issue
of Contractor Tools and Supplies
magazine.
back
to top
|