|
The
hottest job around
Cleaning
up legacy waste from the Hanford Site’s plutonium production
facility offers design, construction and environmental challenges.
It’s the largest construction project underway in the United
States.
by
Clair D. Urbain
If
you think you have waste problems on your jobsite, then ponder the
challenges faced by contractors on decommissioning the Hanford
Site’s plutonium production facility.
The
586-square-mile Hanford Site near Richland, Washington, is bordered
by the fast-flowing Columbia River. Physical challenges include more
than 53 million gal. of radioactive and hazardous liquid waste in
177 underground storage tanks, 2,300 tons of spent nuclear fuel, 12
tons of plutonium in various forms, about 25 million cu. ft. of
buried or stored solid waste, and about 270 billion gal. of
contaminated groundwater. This is spread over 80 square miles on
more than 1,700 waste sites and in about 500 contaminated
facilities.
According
to Department of Energy (DOE) reports, the site produced 64 metric
tons of weapons-grade plutonium since 1945. The production process
left a legacy of radioactive and other hazardous wastes that must be
managed for thousands of years.
The
Hanford Environmental Restoration Project and Waste Treatment Plant
construction are the key parts of the process to centralize and
stabilize these wastes. The goal is to complete both programs before
2014 and 2011, respectively.
Largest
government project
“This
is a $5.7 billion, 10-year job and we are in the fourth year of the
project,” says John Britton, Waste Treatment Plant deputy manager
for Bechtel National Inc., the contractor in charge of construction
of the liquid waste vitrification plant. The firm is also involved
with cleanup of radioactive burial sites and cocooning nine obsolete
reactors that produced plutonium.
Every
phase of the cleanup effort is huge, but all are dwarfed by the
construction of the plant that will process radioactive liquid waste
and mix it with molten glass, which will then be poured into
stainless steel vessels that will immobilize the waste and make it
easier and safer to handle.
“The
vitrification plant’s Pretreatment Facility will separate the tank
waste into high-level and low-activity waste, then mix it with
silica and other components in a melter and turn it into molten
glass. The glass will then be poured into stainless steel canisters,
sealed, decontaminated and moved into storage,” says Alan Beckman,
deputy project manager at the Waste Treatment Plant.
This
is no small plant. The size of four football fields and 120' tall,
the hazardous wastes will be pumped from the tank farms into one of
four 375,000-gal. tanks in the Pretreatment Facility. Analysts
will identify the ingredients in the waste and separate them with
filters, ion-exchange systems, evaporators and other methods. They
will also formulate the additives to make the radioactive waste into
glass.
“About
80 percent of the tank waste is low-activity waste with 20 percent
of the total radioactivity and the remaining 20 percent is
high-level waste containing 80 percent of the radioactivity,” says
Beckman.
“We
project the low-activity waste vitrification process will produce
1,100 canisters a year and will take almost 12 years to complete.
The high-level waste process takes longer and will produce about 240
canisters a year. The High-Level Vitrification Facility will produce
almost 8,000 canisters before the project is complete,” he says.
The
plant sits on 65 acres in the Hanford Site. “That’s not much
space when you have the equivalent of two nuclear power plants being
built at the same time and up to 2,000 workers on the site,” says
Mel Hill, Bechtel National’s procurement manager for MRO and
equipment.
“There
is more than 1 million ft. of piping and 5 million ft. of cable and
wiring to be installed. The building will be constructed with more
than 250,000 cu. yd. of concrete. The base mat for the various
buildings is up to 8' thick. We are self-performing 90 percent of
the work, and we have nearly 600 pieces of equipment on the job.
“Our
biggest challenge is staging and lay-down of supplies and equipment.
The best way would be to have a 100-acre yard plus a 200,000 sq. ft.
warehouse on the construction site. Instead, we have practically no
lay-down space on the site and only a 30,000 sq. ft. warehouse. We
have 140 acres of lay-down area off the Hanford site and use a GPS
system to locate materials on that property,” he says.
The
complex system calls for design and construction to continue
simultaneously to achieve a start date by 2011.
“This
is a design-procure-build project. We were able to save one year of
construction time by having Chicago Bridge and Iron assemble the
four 375,000-gal. pre-treatment tanks on the site, then flying them
into the black cells after the 60'-high walls were built. There was
only 3' of clearance between the tanks and the walls of the black
cells, so the crane operator had to move the tanks only by
instructions radioed from riggers. We had to use a $3 million,
600-ton crane to do it, but when you consider we spend $500,000 a
day on this site, the crane cost was well worth it,” says Britton.
It’s
been decades since a nuclear-grade project has been built in the
United States and finding nuclear-class workers and suppliers is
difficult. “We must help workers and vendors develop these skills.
We work with the building trades and other resources, like the local
community college, to get people with these skills. We are also
working with suppliers, helping them improve their quality assurance
programs so they can provide us with nuclear-class quality
materials,” says Britton.
Cocooning
reactors takes innovation
Nine
plutonium reactors populate the site and are situated along the
Columbia River. Preliminary plans to disassemble the reactors and
move the highly radioactive cores to the center of the site proved
impractical. Instead, Bechtel Hanford and the U.S. Department of
Energy (DOE) developed a process of cocooning the reactors for safer
keeping, says Daryl Schilperoort, subcontractor technical
representative for reactor decommissioning.
“The
goal of the cocooning process is to reduce the footprint of the
reactor by 80 percent. It involves demolishing the reactor buildings
down to the 4'-thick shield walls that surround the highly
radioactive reactor cores. All remaining openings are sealed with
concrete or steel plate and a new roof is built over the remaining
facility,” he says.
The
demolition work is labor-intensive. “Workers remove the walls
block by block and put them into a skiff box that gets moved by a
crane to the ground. The crane also lifts off roof portions and
places them on the ground for disassembly. “We use a 150-ton
Manitowoc 4000 crane with a 200' boom and 30' jib. This
configuration allows us to reach the middle of the building,”
Schilperoort says. Concrete portions are demolished with a hammer
mounted on an excavator.
A
small utility room is built around the double doors that lead to the
reactor core. “This houses the electrical panels and monitoring
equipment. We weld the doors into the reactor shut, and once every
five years, they are opened so the facility can be checked for any
problems. We recently opened the C reactor, which was the first unit
to be cocooned, and the area was just as it had been left,” he
says.
Schilperoort
has been involved with cocooning three of the four reactors already
completed. Lessons learned on the first reactor have streamlined the
process. “We like to say we now can cocoon four reactors for the
price of three,” says Schilperoort.
Search
for technology
Part
of that streamlining process relates to a program the DOE set up
when the project started, says Kim Koegler, project engineer and
manager of technology application for Bechtel’s Environmental
Restoration Project.
“The
program was designed to identify technologies that help us improve
the baseline of the project from a cost, safety or scheduling
perspective. We developed a needs statement, then looked for
solutions. We first look for off-the-shelf solutions, but some were
also engineered. The DOE wanted us to implement technologies that
had wider applications, but we found that isn’t always
possible,” he says.
The
program that formalized this process has been discontinued by the
DOE, but Bechtel Hanford continues it as a best business practice.
It
also pegs a life-cycle cost savings from many of the technology
deployments. “We have already achieved a life-cycle cost savings
of $137 million,” says Koegler.
Here is a short review of some of the problems and solutions their
technology teams have developed:
Oxy-gasoline cutting torch. Uses
gasoline instead of acetylene as fuel and offers lower cost, higher
temperatures and faster cutting of metal thicker than 1". From
Petrogen Inc., the unit reduces airborne contamination and increases
worker safety. It is readily available and less costly to use than
an oxyacetylene torch.
Body core temperature monitor. Workers
in highly contaminated areas must wear several layers of protective
clothing. Site temperatures can top 100 F and although workers wear
cooling vests, it was not clear how long workers could remain in the
suits before heat affected them.
The
Body Core Temperature system uses a pill-sized Cor-Temp monitor that
the worker swallows. A palm-sized monitor tracks internal body
temperature. This data can be downloaded for analysis.
Data
from the study indicated that workers could work up to one hour
longer than originally allowed. This ensured personnel safety,
reduced cost and improved scheduling by optimizing safe work times.
Estimated lifetime cost savings/avoidance: $1.4 million
Affixing contaminants. Dismantling tanks with radioactive sediment have a
high risk that contaminants will become airborne. To affix the
contaminants, Rust Doctor, a water-based latex paint, is applied
inside the tank. The paint converts iron oxide into black magnetite,
which captures and fixes the radioactive contamination to the tank
walls for safer dismantling. Estimated life-cycle cost
savings/avoidance: $1.254 million.
Fogging system to settle demolition
dust. While
the Rust Doctor paint affixes contamination inside the tank,
demolition could cause airborne contamination that could reach the
Columbia River, which was only 200' away. To reduce airborne
particles, a Mini-Pro fogging system that uses a 5 hp. Briggs
engine, a 100 cfm Roots blower and a Fluid Metering Inc. pumping
system sprays a glycerine coating that settles out airborne
particles in the controlled area. The Mini-Pro fogging system can be
positioned up to 50' away from the work area.
Dust control on service roads. Some
roads on the sites are unpaved and dusty. While watering roads helps
control most dust, some areas require greater dust suppression. In
these areas, crews apply Dust Bond, a cohesive resin, diluted with
water. When sprayed on roadways, it penetrates the surface and
attaches to fine dust particles. It offers less labor because less
watering is needed and reduces road maintenance because it
stabilizes roadways. It won’t get picked up by tires or shoes, is
non-corrosive and will not leach or wash from the soil. Estimated
life-cycle cost savings/avoidance: $51,000.
Motorized cart simplifies lifting. Heavy,
bulky items must be moved by hand in the decommissioning and
demolition process. It sets workers up for back strains and other
injuries. The Ultra Lift is a powered two-wheeled handcart that
allows users to move heavy objects easily. It can traverse steps and
can handle loads up to 1,500 lbs. and 36" high. Estimated
life-cycle cost savings/avoidance: $61,000.
Remediating
burial sites
With
60 years of plutonium production, contaminated parts and materials
are unavoidable. During the height of production, the radioactive
parts were simply buried on the site in controlled areas. Under the
contract, these areas must be excavated and the hazardous material
moved to the Environmental Restoration Disposal Facility (ERDF), a
state-of-the-art, engineered landfill designed specifically for
CERCLA low-level radioactive and hazardous waste. It’s in the
center of the Hanford Site.
“There
are not good records of where things are buried. Burial grounds and
waste sites range in size from a few sqaure feet to the size of a
football field. They contain everything from demolition debris,
reactor parts, tubes of mercury used in tritium processing to gun
barrels used in plutonium production. It’s a real junkyard,”
says Rex Miller, task leader at the 100 B/C area burial ground
remediation project. “Many parts are highly radioactive and could
cause high-dose exposure.”
Excavator
operators digging up the burial grounds wear Level B protective
equipment with supplied-air respirators. Sensors on excavator
buckets monitor radioactivity and operators sort the excavated
material by its level of radioactivity. When the excavator is not in
use, the potentially contaminated bucket is cordoned off and posted
with radiation hazard signs.
The
excavator operator cascades the soil onto piles of like materials.
Suited workers sort out any metal or other parts with long-handled
rakes or staffs.
“In
the burial grounds, we dig until we find native soil,” Miller
says. “We have twice as much radioactively contaminated materials
as we were expecting to find in some of the burial sites.”
Once
all contaminated material is removed on a portion of the site, the
area is sampled remotely for radioactivity. “We file reports with
the DOE. Once they confirm our findings, we can fill in the
excavated areas,” Miller says.
The
radioactive material is placed in special containers that move it
from the site to a transfer station. The containers are
decontaminated and over-the-road trucks take them to the ERDF for
disposal.
The
ERDF is made of up of four cells. Cells 1 and 2 are already filled
and Cells 3 and 4 are nearly filled. Construction is nearly complete
on Cells 5 and 6. The ERDF is designed to be expanded as needed, and
the site could accommodate as many as 30 cells. Once the ERDF is no
longer needed, a permanent cover will be designed and placed over
the whole disposal site.
Editor’s note: Find out more at
www.waste2glass.com
or
www.hanford.gov.
Published
in the November/December 2004 issue of Contractor Tools and Supplies
magazine.
back
to top
|