|
“Lean”
construction
Grunau
Co. takes lessons learned in manufacturing and adapts them to the
mechanical trades.
by
Clair Urbain
Lean
manufacturing is all the rage in plants across the country. In an
extremely competitive environment, streamlining plant processes and
eliminating waste are battle cries for survival.
Construction
is also competitive, but there hasn’t been the rush to apply
similar lean principles to achieve greater productivity and quality,
and Ted Angelo has set out to change that at Grunau Co., a
Milwaukee, Wisconsin-based mechanical trades contractor.
Angelo
was turned on to lean construction concepts a few years ago after
hearing about it at an association meeting. In less than two years,
the tools he has learned and shared with others in the company have
resulted in dramatic changes in how they tackle work.
The
new way of working has yielded at least $59,000 in tool cost savings
in the toolroom in one year; an on-the-jobsite vendor stocking
program has reduced parts costs by $45,000 in six months; and
changes in weld and sheet metal shop work flows have yielded up to
20 percent savings.
“This
does not even include the savings from faster order filling,
increased utilization of tools and other
improvements in productivity,” says Angelo, Grunau’s
executive vice president.
“I
have had people say, ‘Lean concepts won’t work in construction.
Every job is different.’ I reply, ‘How many soldered joints do
we do on a typical job? Tens of thousands? Do we do each one of them
differently?’ It’s really about best practices and continuous
improvement and that’s how we look at lean construction,” says
Angelo.
Train
the trainer
To
become versed in lean concepts, Angelo attended a Milwaukee School
of Engineering Lean Manufacturing certificate program where he
rubbed elbows with people from companies adopting lean practices. He
also attended training offered through the Lean Construction
Institute and read many books on the subject. The company also hired
a consultant to help steer the effort.
“Management
commitment is important. We train every employee in the benefits and
practices of lean construction. When you have 500 employees, that is
a huge commitment. We think it is worth it,” he says.
The
5 S concept is one of several tools Grunau’s lean team uses to
improve processes. In training its cross-functional lean team, the
group decided to reorganize the toolroom as its first project in
September 2003. Since then, the team has tackled many other projects
and Angelo hopes to have worked through the list of 60-plus projects
by 2008.
“We
selected the toolroom as our first project because it would have a
great impact on the company from a business standpoint and have a
‘wow’ factor,” he says.
|
Elements
of 5 S
The 5 S concept originated in Japan, and this is a rough
English translation of what the 5 S concept signifies. These
are the steps that Grunau Co. took to make over its toolroom,
prefab areas, warehouse, storage yard and toolboxes.
Sort:
Sort from the workplace what is needed from what is not
needed. General criteria: If it wasn’t used in the last 30
days or will not be needed in the next 30 days, store it
away from the worksite. Grunau uses a red tag to signify
items that must be removed.
Straighten/Set
in order: Find a place for everything and put everything
in its place. Mark and label everything so it can be easily
found and put away.
Sweep/Shine:
Clean the area and the equipment. Use a “ceiling down”
strategy. Paint if necessary and develop strategies to
prevent items from getting dirty.
Schedule/Standardize:
Standardize the use of the first three steps of the 5 S
process by developing checklists (work instructions) for all
areas. Checklists should include a picture of what the area
should look like.
Sustain:
Make the first four steps of the 5 S process a part of
company culture. Use an audit team to evaluate and grade the
5 S implementation throughout the plant. |
The
toolroom and warehouse were the dumping ground for tools and
supplies coming back from jobsites. The toolroom supervisor was in
charge of organizing the material so it could go to other jobs.
Without a structure or system, it was difficult.
The
12-person cross-functional team applied 5 S principles to the
toolroom. The team looked at the inventory of parts and realized
that once parts came back to the shop, it was highly unlikely they
would ever get back out on a job. “We would spend more time
looking for the item than what the item was worth,” says Angelo.
A
healthy housecleaning and a switch to bin-fill arrangements with
distributors on jobsites resulted in the company eliminating half of
the racking in the warehouse.
Tool
organization was driven by the number of footsteps it takes to fill
an order. “The team counted the steps it took the toolroom
supervisor to fill an order. Starting off with 525 footsteps, they
reorganized everything to reduce footsteps to 252. We believe that
footsteps equal time which equals money,” Angelo says.
The
toolroom, once a general area, is now set up supermarket style with
racks plainly marked for dedicated tool storage. The whole area was
clad in white metal for better light reflection and bins were
painted white inside and out to make bin and shelf contents easier
to see. Every cubby and shelf space has an easy-to-read label.
The
team revisited the toolroom process in September 2004, and
fine-tuned it even more.
“Lean
and 5 S isn’t about getting it 100 percent right the first time.
It is about continuous improvement. We conduct monthly audits of
processes and post the results. It’s the final and critical step
in the 5 S process to assure it is sustained,” he says.
The
team has also reworked the welding and sheet metal shops for greater
flexibility. For example, rolling stands for pipe cutters and
threaders stand like sentinels along the wall of the shop, ready to
be rolled into place on tracks made of inverted channel iron. All
tool storage areas are marked clearly and are stored in that place.
On
the jobsite
The
lean team also develops lean practices for the jobsite. Any area or
activity is fair game.
Any
lean proposal is circulated in the company. “We have apprentices,
foremen and service technicians look at what we are thinking of
doing to get their perspective. Fresh eyes see things that those
closest to the project may miss,” says Shane Schilcher, piping
superintendent.
Gerry
Gelhaar, one of Grunau's general
foreman, is a 30-year veteran of construction and sees the benefits
of standardizing procedures. The lean practices on the jobsite
reflect activities on other Grunau jobsites:
Last
Planner®: “We use a system called the Last
Planner®. It’s a
philosophy that no one knows better about what it will take to do a
job than the workers doing it. It takes a six-week look into the
future and once a week, we review the steps and number and type of
workers required to complete those steps,” says Gelhaar. “It’s
all tracked on an Excel spreadsheet that I update weekly and share
with all parties involved with this job,” he says.
Schilcher
says the Last Planner® concept helps him see where the pipe fitters
and sheet metal workers are working and allows him to look for
coming bottlenecks on the project.
“Other
contractors use other programs and methods to manage work, and
sometimes their work interferes with ours. We can’t control that.
But if we can do a better job of managing the work we can control,
we will be more efficient,” he says.
Bin-fill
agreement with a distributor: The bin-fill arrangement instituted on
jobsites sets up a kanban system with minimum and maximum
quantities. A tool and supply distributor restocks the cabinets
every week. From job to job, the cabinets are stocked in the same
order so workers transferring from one job to another don’t have
to learn a new scheme. When the job is finished, the cabinets go
back to the distributor, and Grunau only pays for the parts consumed
on the job.
|
Secrets
to
Grunau’s success
Ted Angelo shares key points needed to successfully adopt
lean concepts in any organization:
Understand
it. Angelo suggests reading, attending conferences and
talking with others instituting lean practices.
Commit
to an outside consultant. It costs money, but an expert
in lean techniques can help others understand it, knows
where pitfalls and resistance may lay, and can lead the
company through the all-important first projects that make
the biggest impact on the company from buy-in and
money-saving standpoints.
Commit
to the process. This must come from the top and filter
throughout the organization. “We struggled at first, but
then ended up training everyone. We found that if we
didn’t, the rumors would fly. Do everything to show
commitment to the process,” says Angelo. Keeping the
process highly visible in the organization also shows
commitment and respect for the teams’ efforts.
Create
a passion for the process. It’s a tremendous challenge
to lead change in an organization. Rely on respected
authorities in the organization to help carry the concept.
Embrace
change. Understand that even processes transformed by
lean events can be improved. Tackle them again to make them
even better.
Keep
it simple. It’s really all about common sense. When
transforming processes, find the simplest, and often least
expensive way to make changes.
Keep
it going! Angelo says this is the most difficult part
ofthe process. Audit the process regularly and post audit
results to show progress or deviations to the process. |
“We
don’t need an apprentice or foreman ordering parts for each trade.
It’s all ordered the same way and the parts are all here, and
workers just take what they need for the job. In exchange for giving
one distributor the business, we don’t have to deal with ordering
and stocking and can be more productive on the job,” says Gelhaar.
For
greatest efficiency, supervisors review tool and supply consumption
after every job and continue to streamline the inventory. “For
example, we only buy 6" bolts and cut them down to the length
as needed. This saves room in the cabinet and makes stocking
easier,” says Schilcher.
Trades
toolbox: The latest project underway is developing a two- or
three-man trades tool box that is standard issue for every jobsite.
In it, tools are sorted by type and trade and stored in a labeled
spot in the toolbox. Any Grunau worker can open the box and find a
needed tool quickly (see illustration).
“It’s
still in the design phase and we are circulating the concept for
input. We’ll put it together, find out how it really works, then
fine-tune it,” says Schilcher.
Job
supply carts: Grunau has assembled some job-specific carts. For
example, it built wheeled carts that neatly hold fittings for fire
sprinkler installation. The parts are easy to find, access and
review for restocking.
Stop
the band:
In the past, prefabricators would band prefabricated pipe
before shipping it to the jobsite. Now, prefabricators place the
pipe on 6' wheeled tree racks that are rolled onto a truck for
shipping. “Transportation is a bit more expensive, but the huge
reduction in onsite labor makes more sense because we aren’t
banding and unbanding pipe anymore,” says Angelo.
Worker
acceptance
Some
naysayers believe that lean construction is the flavor of the month,
soon to be replaced by another management fad. Not so with lean
construction at Grunau. In fact, workers embrace the concept.
“Workers
like it because they can get their tools quickly. It also makes them
feel more professional because the contractor is doing something to
make their job easier, not harder,” Gelhaar says.
“It
all adds up to a winning team concept. If workers can get the
information, tools and parts so they can do their job, they feel
better about the job they’re doing and appreciate it,” Gelhaar
says.
Published in the
March 2005 issue
of Contractor Tools and Supplies
magazine.
back
to top
|