|
Lofty
goals
Renovating
100-year-old H.J. Heinz factories and warehouses into luxury loft
apartments yields building challenges -- and new living space -- in
downtown Pittsburgh.
by
Clair D. Urbain
Pittsburgh
continues to be considered an icon of the born-again Rust Belt. The
rebirth of its industrial yards is remaking the city into a vibrant
financial and services center that is attracting new money while
recycling old buildings built nearly 100 years ago.
The
food-processing giant, the H.J. Heinz Company, has its roots on the
banks of the Allegheny River in downtown Pittsburgh. Known around
the world, the multi-billion dollar company sells products ranging
from its world-famous ketchup to Ore-Ida potatoes.
As
the company grew in the early 20th century, it built a variety of
buildings at what is now known as the North Shore area of
Pittsburgh. The five- to seven-story buildings were built to last
the ages and are typical of the German Romanesque architectural
style of the city.
Stately
and strong, they were built to help the growing food processor meet
customer demand. However, they outlived their usefulness as
efficient production facilities as they aged into the 21st century.
A
new life
Ironically,
as the buildings’ usefulness as production facilities waned,
demand for downtown housing burgeoned, especially along the
picturesque Allegheny River. The Ferchell Group, a developer that
has taken other old manufacturing and warehouse facilities into the
21st century as upscale housing, purchased five of the Heinz
buildings for renovation.
The
buildings, still known by the names of their original use —
Shipping, Bean, Meat, Reservoir and Cereal — are being reborn as
trendy and unique one-, two- and three-bedroom loft apartments.
Construction
for the $70.2 million H. J. Heinz Lofts project began in January
2003, with completion slated by January 2005. Funding comes from a
variety of sources, including HUD and the AFL-CIO’s Housing
Investment Trust.
Four
of the five buildings on the four-acre site will be developed into a
total of 267 apartments. The Shipping building will be transformed
into a parking garage. Enclosed bridges, once used to move product
in and out of the manufacturing facilities, will now protect tenants
from the weather as they go from building to building. The ground
floor of the Reservoir building still houses offices and equipment
for Heinz’ parent company, Del Monte.
Renovation
challenges
Renovating
the structures provides some interesting challenges for architects
and contractors, says Bill Jacob, foreman for Miller Electric
Construction Inc., which has the contract to help the demolition
contractor remove old wiring. Then Miller crews will rewire the
complex.
“Removing
power from the buildings was difficult. Power would feed from one
building to the next. We would turn off a breaker in one building
and the lights would go out in an area that was two buildings away.
We were constantly concerned with power back-feeding from other
circuits,” says Jacob.
“It
took us a few months to assure power would be safe. We went from box
to box, testing circuits. We painted any conduit or wire that was to
stay green; any to be removed were painted orange. Our plan was to
remove all power except for one high-voltage line in each building
during construction. When the new power was in place, we would then
remove the old high-voltage line,” he says. “If the demolition
contractor was ever uncertain about the line, he would ask us.
Fortunately, we have had no surprises as demolition progressed.”
The
demolition process took the buildings down to their shells. Windows
that help define the buildings’ architecture were removed,
refurbished and replaced.
To
create dramatic lighting on the buildings, Jacob’s crews had to
strategically place conduit so the uplights that illuminate the
buildings’ facades would be correctly positioned. “The walls are
36" thick, so we started drilling from the outside with a
special-ordered 42" bit. It would take us an hour and a half to
drill one 5/8" hole. We had to watch where the bit would end up
because several of the holes had to be angled to miss support beams
inside the building,” he adds.
Establishing
new distribution lines in the buildings required crews to core-drill
5"-diameter holes through the old foundations. “We had to
make 30 power entrances in the buildings using core drills with
extensions. All the conduit coming into the building will be encased
in concrete and will feed switchgear that will power each
building,” Jacob says.
The
loft apartment style calls for open spaces and exposed bricks and
beams. To create that effect, architects required that electrical
and mechanical services be unobtrusive in the apartments. “We used
to take ceilings for granted but this job has given us a whole new
appreciation for them. These apartments have exposed ceilings in
most of the areas and no wiring can run across them. In most of the
apartments, only the bathroom has a finished ceiling and that’s
where the electrical and mechanicals are run.
“We
are running wiring around walls because there is no finished ceiling
where we can run conduit. We have some runs that are more than 100'
longer than they need to be because there was no ceiling where we
could run wire.
“It
took extensive pre-planning and coordination with all of the trades
to get the utilities in place because all of the mechanicals and
electrical service must run through the same space,” he says.
“Every building, every floor is different, so it’s hard to
establish a work pattern that gets it all finished efficiently.”
In
most apartments, the mechanical and electrical service runs under a
raised floor that requires one or two steps in the apartments’
main hallways. HVAC systems either tuck into the ceiling above the
bathrooms or in a utility closet. Further, all floors get an
additional layer of concrete to seal residue and allow for plumbing
recesses.
Finding
consistency among the variables
“Front-end
planning is the key to the success of this job,” says David
McKamish, president of McKamish, the project’s mechanical
contractor.
“This
is a design-build job that required extensive initial budgeting for
funding. It took one and one-half years to get the design
development complete to secure funding. The design was almost 95
percent completed before funding was established,” he recalls.
“Although
this is a retrofit job with many unique challenges, the work is
highly repetitive. It is a job with a lot of duplication and that
means pennies, seconds and minutes add up. For example, a $100
problem is not just a $100 problem. It is a $100 problem multiplied
267 times, so pennies and nickels quickly add up to dollars. We have
instilled this thinking from the design to the installation
process,” he says.
“Initial
plans called for only 12 distinct apartment configurations, but once
all buildings were site-surveyed and design changes made to account
for individual building designs, we ended up with 67
configurations,” says McKamish.
“With
that many variations, prefabbing is more difficult. We worked hard
to figure out the best way to install the mechanicalsin the first
building and are proceeding with that plan in the other
buildings,” he says.
Work
crews were challenged by a layer of tar sandwiched between layers of
concrete in the floors of some of the buildings. The floors are from
13" to 18" thick. “It was put there for waterproofing,
and once a core drill hits it, it gums up so badly that workers must
stop and clean the core. Now, crews look for telltale signs of tar,
such as tar residue at the base of columns, then go more slowly and
clean out the hole more often while drilling.
“As
soon as they encounter tar, they stop and clean out as much as
possible or flood the hole with water to keep the tar cool so that
it doesn’t melt and gum up the bit. We are making more than 3,000
holes this way,” he says.
Rich
Moore, McKamish sheet metal foreman, concurs with McKamish about the
challenges of the job.
“This
job is different than new construction. We had to field-survey all
existing conditions and then build around them. From there, our
engineers use CADD to lay out the duct work configuration and then
we evaluate our prefab opportunities for the sheet metal work. We
are fortunate that our shop is only 10 minutes from the site,” he
says.
Moore
agrees consistency helps all of the contractors do their jobs more
efficiently. “The key is preplanning. We all have to come up with
a system and procedure that allows us all to do the job the same way
every time. On this job, it took us the first building to get it
down right, but on other jobs, we look to get the process in place
on the first floor of the first building,” Moore says.
Like
the electrical service, ductwork must be installed in a way that
adds character to the apartments. “We are using lasers more on
this job than any other job we’ve had,” says Moore. “Since
there is so much exposed ductwork, we lay it out on the floor then
use the laser to shoot up to the ceiling to mark the spots where the
hangers must go. This saves a man on the job because we don’t need
someone on a ladder with a plumb bob,” he says.
The
lasers also aid in transferring pipe locations from floor to floor.
“We
took a piece of Plexiglas and drew circles of various diameters on
it (see illustration). The circles line up to a cross-hair and in
the center, we drilled a 1/4" hole. To transfer the spot to the
floor below, we align the Plexiglas template with the proper hole
size, then shoot the laser down through the hole to the floor below.
There’s only one mark needed, and it eliminates using two
measuring tapes and plumb bobs and the worry that there are
variations in walls from floor to floor,” he says.
Teamwork
for success
McKamish
believes the success of this project lies in the spirit of the
teamwork that evolved as this job went through design development
with the architect, developer and general contractors. “We also
had the same people working on the project from front to back, and
that continuity helped build a teamwork approach. Putting people on
and pulling people off the job throughout this process would not
have worked so well,” McKamish concludes.
Published
in the July/August 2004 issue of Contractor Tools and Supplies
magazine.
back
to top
|