|
Marquette
Interchange makeover
Rebuilding the
Marquette Interchange in Milwaukee without crippling traffic takes
planning and timing.
by Clair D. Urbain
As the North Leg of the
project nears completion, the project is on time and on budget.
The ability to move
hundreds of thousands of cars a day along the west shore of Lake
Michigan and in the heart of Milwaukee proves the Marquette
Interchange is definitely the lifeline of Milwaukee’s – and all of
Southeast Wisconsin’s —transportation system. As the busiest
transportation hub in Wisconsin, it funnels traffic into and out of
Milwaukee, to and from Chicago and other points in Illinois to the
south, Green Bay and other points to the north, and southcentral
Wisconsin and the upper Midwest to the west.
However, ever-increasing
traffic on the 40-year-old interchange has outgrown it and the
ravages of time and travel have simply worn it out.
In 2002, officials at
the Wisconsin Department of Transportation (WisDOT) proposed an
interchange modernization that would cost $810 million and, without
proper planning and execution, could cripple businesses and
commuters throughout the western edge of Lake Michigan.
Strategic location
The Marquette Interchange lies smack-dab in the middle of
Milwaukee’s regentrifying downtown area. Built in the late ’60s,
it’s where I-794, I-43 and I-94 converge. Its original design was
built to handle 150,000 vehicles a day.
WisDOT officials
estimate traffic flows at more than 300,000 vehicles a day, with
traffic projected to grow to 375,000 vehicles a day within the next
20 years.
The project has a 2008
total completion date. It is divided into five sections and the work
on the first sections that began in early 2004 will be completed in
late 2006. The reconstruction of the North Leg is being completed by
Walsh Construction’s Chicago Heavy Highway Group, reports Paul
Bentley, assistant project manager.
“The Marquette
Interchange North Leg is a $102 million portion of the total $810
million project. It’s a 26-month project that started in October
2004 and will finish in November 2006. The project is approximately
85 percent complete and is on schedule,” he says.
The North Leg runs from
Wells Street overpass to the North Avenue exit. It is the total
reconstruction of the I-43 north and south lanes plus ramps, bridges
and other infrastructure such as retaining walls and water and sewer
lines. The 1.5 miles of interstate highway it covers vary between
three and four lanes, with elevations changed to improve visibility
and traffic flow.
Non-linear project
“This particular project is not very linear in nature,” says
Bentley. “Keeping at least two traffic lanes open in each direction
while removing and replacing retaining walls, bridges, water and
sewer lines and building and grading the new roadbed and ramps meant
we had to schedule work differently. You cannot simply start at one
end of the project and work toward the other end. The staging
requires you to be in several places at once,” he says.
“We have this job
organized in three basic divisions: structures, earthwork and
roadway. We divide it that way and each type has its own manager who
controls the subcontractors working on that aspect of the project.
However, we act as a unit.
“Every day, there is a
scheduling meeting with Walsh and its subcontractors to talk about
the next day’s work activities and upcoming major schedule events,”
he says.
“The phasing of
construction for staging is very structurally driven. The 75,000
linear ft. of secant pile drilling required drilling 36"- to
60"-diameter pilings from 15' to 80' deep. We drill two primary
shafts and then drill a secondary shaft between them to form the
secant design of the retaining wall. This had to be completed in
many areas before roadwork began.
Varied soil
conditions
“The soil conditions vary greatly in this 1.5-mile segment. It goes
from solid clay to sand and it’s very sporadic over the job and, in
many areas, the water table is high.
“All of the secant pile
drilling has been completed. Due to the cost of the drilling
equipment, we were able to leverage its time by moving it into
certain areas earlier to help meet our project deadline,” he says.
Pre-cast concrete panels
or cast-in-place concrete walls are installed over the secant pile
retaining wall system to improve its visual appeal. This is an
important part of this project because it puts a new look on this
post-industrial city.
Friezes add interest
On bridge overpasses and exit and entrance ramps, larger-than-life
friezes depict the working heritage of Milwaukee. The design also
requires decorative reveal lines in the concrete walls that cover
the secant walls as well as into edges of overhead sign foundations
and bridge supports. The reveal lines are added with block-out
sections that are attached to the forming system. The friezes and
concrete walls will be stained a warm golden color to brighten the
new concrete canyons that bisect the city.
The North Leg project
features nine bridges that had to be demolished and rebuilt.
Throughout the project, lanes are being added, ramps are
reconfigured and elevations are being adjusted for greater
visibility and traffic flow.
“We are moving
approximately 850,000 cu. yd. of total earth to get the new roadbed
on the North Leg to the proper elevation. In some areas, the road
elevation has changed by as much as 20'. There are new ramp systems
that replace old ones, each offering right-hand exits, longer
acceleration and deceleration lanes and smoother curves to promote
the flow of traffic. Walsh has 43 subcontractors on this project and
coordination is needed to keep this on track.
“The removal of the
Milwaukee County Court House Annex parking structure was a new twist
to our schedule. With the removal of the parking structure, the DOT
added an additional lane that was not originally part of the
contract. This created some new scheduling challenges, but we were
able to reshuffle to allow for work to meet the scheduled completion
date. Since we control both jobs, we can control the schedule better
ourselves,” he says.
Final demolition of the
annex was briefly delayed when four gulls began nesting on a portion
of the structure in May. Permission from federal authorities allowed
demolition to proceed.
The existing roadbed is
being replaced with asphalt laid over an aggregate sub-base. “Some
of the aggregate will come from concrete salvaged from the parking
structure demolition,” Bentley says.
Insurance approach
This is an owner-controlled insurance program (OCIP) project, says
Bentley, which provides insurance coverage for the project rather
than the contractor providing its own insurance package.
“It is an interesting process. Every worker on the site has to
attend a mandatory safety orientation and complete a drug screening
before being allowed on the site,” he says.
Traffic moves on
Compared with other metropolitan areas, traffic continues to flow
well through the interchange during rush hour, even as it’s being
squeezed into two lanes and while entrance and exit ramps and
bridges are being rebuilt.
Published
in the July/August 2006 issue of Contractor Tools and Supplies
magazine.
back
to top
|