|
On
the Red Line
Expanding
the Metro mass-transit system in Washington, D.C., takes some new
turns as it builds the New York Avenue station on the Red Line, the
city’s busiest rail line. The design-build project should be
completed in 2005.
by
Clair Urbain
The
near-northeast side of Washington, D.C., will soon become a
destination instead of a forgotten neighborhood. The area, vibrant
in the first half of the 20th century, is one of the Capitol’s
most blighted neighborhoods today. The construction of Metro’s New
York Avenue station will give the old neighborhood immediate access
to mass transit that promises to attract new buildings, new
businesses and new life.
Historic
past
The
area has long been a pass-through area, with Amtrak, Metro and MARC
trains whisking passengers through the northeast side of the city,
says Damian Ruppert, project manager for Slattery Skanska. Slattery
Skanska and Lane Construction have established a joint venture to
work with the design firm, Jacobs Engineering, and the Washington
Metropolitan Area Transit Authority to build the $103 million
station.
The
neighborhood can only get better. The U-Line Arena, where the
Beatles performed their first act in the United States, stands empty
next to the train line, most recently used as a garbage transfer
station.
On
the west side of the station’s site, little remains of the
businesses between M Street NE and New York Avenue. The rail
trestles in the coal yard, where Pennsylvania coal came in on rail
cars, are long gone and the contaminated soil from years of coal
dumping has been removed or remediated. Trees that took over the
abandoned yards have been removed and the neglected area will soon
be home to the U. S. Department of Alcohol Tobacco and Firearms’
new building to be built next to the new train station.
“Slattery
has been involved with building the Metro in Washington, D.C., as
well as lines in Boston, New York and Atlanta. This is the first
time that Metro is expanding the line within the system. All other
expansions have been at the end of established lines,” he says.
Building
a new station along existing, very busy rail lines presents some
significant challenges to designers, contractors and workers.
Typically, a train runs by the site every six minutes.
“This
is called an in-line or fill-in station because it is in line with
the existing operating line,” says Ruppert. “This is the first
time that Metro has built a station on rail line that is already
running.”
Site
preparation
Slattery
Skanska was involved with the site preparation, which took one year
and cost over $5 million. “We had to remove 100,000 tons of
contaminated soil where the coal yard was, plus remove heavy brush
that grew on the site. When it was cleared, everyone remarked that
you will be able to see the dome of the Capitol building from the
station platform. It will become very attractive real estate,” he
says.
The
Metro station construction falls within 12' of the operating rail
lines. “In the New York City subway system, most of the lines have
two sets of double tracks, one for local trains and another set for
express trains. The two sets of tracks allow shutting down one line
temporarily for work or maintenance. But the Metro’s Red Line has
only two sets of tracks, so there is no way we can reroute the
trains or shut the line down for any length of time. The line must
stay available throughout construction,” he says.
The
project stretches over 1,650' long next to the present tracks.
Because the station sits only partially on the built-up bed for the
train track, the western side of the station, tracks and bicycle
path must be built on an elevated structure. Slattery Skanska is
self-performing about 60 percent of the work, most of it
cast-in-place concrete.
“To
stabilize the railroad bed and protect the existing track, we had to
drive 800 linear ft. of steel sheeting and tie it back under the
railroad bed. This assured the railroad bed remained stable as we
built the retaining wall for the station. The sheeting was left in
place after the retaining wall was built and we backfilled right
over it,” he says.
The
west side of the station, which will accommodate trains going
downtown, is being built on columns and reinforced pre-cast concrete
beams. “The track must transition off its present alignment, then
over Florida Avenue on an overhead bridge that will be repositioned
to carry the track onto the elevated columns.
“We
have to extend the bridge abutments another 20', then we will pick
up the 194-ton bridge and place it on the new abutments. This should
be completed before the end of the year,” he says.
As
engineers looked at installing the abutment for the transition
bridge, they considered driving pre-cast concrete piles into the
ground near Florida Avenue. “But a closer inspection revealed a
120-year-old brick sewer that might collapse from the drilling
operations. So instead, we went with poured caissons to support the
abutment and elevated train track,” Ruppert says.
Anyone
working with cranes or on scaffolding near the track must follow
specific rules to minimize the chance that any material would fall
onto the track. Workers are also trained about proper grounding
procedures needed around the electrified third rail that powers the
passing trains.
Because
the frame of the structure is made with pre-cast components, the
54-ton platform beams and 49-ton cross beams had to be put in place
at night when trains are not running.
It’s
a bicycle station, too
The
new train station will also be a key link in the eight-mile
bicycling/hiking corridor between the Union Station downtown with
the suburbs in Silver Spring.
“The
station has two bicycle path access points that allow users to roll
their bikes onto a specially designed groove that makes it easy for
bikers to take their bikes up the steps.
“In
the original design, we were going to cast these steps in place, but
because of the design-build approach on this job, we reconsidered
doing that and decided to use pre-cast steps. Using pre-cast steps
allows us to save some significant time and money,” he says.
“Slattery
Skanska has done many design-build projects, but this is only my
second and it is Metro’s first. I really like it because we are
located in the same field office as the owner. If we need to make
any changes, we go downstairs and talk about it. We can make changes
very easily. We have found several ways to do the job more
efficiently and safer than what we had first envisioned,” he says.
To
bring the station online in phases, the first inbound track will be
connected and put into service over a three-day weekend. The new
outbound track will then be constructed where the old inbound track
used to run. Then, over another three-day weekend, the new outbound
track will be put into service and the station will be operational.
“What
makes this unique is that at every phase of the operation, it must
be certified that the automatic train control system is fully
operational. It must go like clockwork because we can’t have the
Red Line out of service at any other time. If that happens, we pay
liquidated damages,” Ruppert says.
Funding
“This
is the first Metro project that uses a mixture of public and private
funding,” says Ruppert. “The federal government is paying $25
million; private partnerships that include neighborhood developers
are paying $25 million and the District of Columbia is paying $40
million. The Washington Area Bicycle Association is also paying $6
million for the design and construction of the bike trail component
of the job,” he says.
Published
in the March/April 2003 issue of Contractor Tools and Supplies
magazine.
back
to top
|