|
Pave
the way
by
Clair David Urbain
Vee-Jay
Cement Contracting Co., Inc. uses 3-D screeding to achieve complex
slopes, yet maintain concrete flatness on a variety of jobs at the
Lambert St. Louis International Airport.
The
Lambert St Louis International Airport is undergoing a $1.109
billion metamorphosis. More than 1,500 acres of developed property
has been purchased, and the airport authority is adding another
runway that will increase its size and capacity by almost 50
percent. The changes will allow planes to land simultaneously in all
types of weather.
To
make room for the new runway, almost 2,000 residences and 70
businesses were purchased and nine major roads in the area are being
rerouted. One cemetery was totally relocated and enough soil to fill
in Busch Stadium three times over – 8 million cubic yards – will
be moved using state-of-the-art earthmoving equipment that almost
eliminates the need for traditional surveyor’s stakes.
The
first highway tunnel built in Missouri will move traffic on
Lindbergh Avenue underneath the new runway, and the road
reconfiguration will straighten many roads, improving capacity and
highway safety.
New
roads, new construction methods
With
the area’s highway infrastructure getting a big makeover, the
Missouri Department of Transportation (MODOT) has set some high
standards to assure the new roads will drain well, offer a smooth
ride and last a long time.
“MODOT
now requires very flat road work, holding tolerance to 1/8" in
10' for non-profilograph pavement. Their thinking is with a smoother
road and fewer bumps, there will be less shock force as traffic goes
over the road,” says David Barnes, who handles safety, quality
control and mix designs at the St. Louis-based Vee-Jay Cement
Contracting Co., Inc.
Vee-Jay
has several subcontracts on the airport project. In 2003, the
contractor was involved with four major jobs taking place at the
same time. With heavy rains last spring, the work crews lost about
40 days of work time. “But the completion dates didn’t change.
You can’t make up for that much lost time, but we have managed to
stay close to schedule,” he says.
To
meet the demands of the tighter specifications and timeframes,
Barnes says the company has taken a next-generation strategy with
equipment, and the strategy is working.
The
work Vee-Jay is doing at Boeing’s new Phantom Works plane assembly
facility requires even tighter tolerances than other jobs. The FAA
specifications require a straight-edge test of 1/8" in 10' in
all directions on the apron.
“We
are pouring all of the concrete outside of the assembly hangers as
well as the paint booths and hush houses, where assembled airplanes
are strapped down and taken up to flying speed for testing before
they are commissioned to fly. FAA spec requires the areas to have
less than one percent of slope because it is so easy for the
airplanes to roll. Still, the water must be able to drain off, which
meant that many parts of the apron had to be sloped in two
directions to get the proper run-off,” he says.
What
first looked like a job that would require intensive forming for
alternate paving lanes, the staff at Vee-Jay got together and
explored some cutting-edge technology that could significantly cut
labor and maintain accuracy.
“When
we bid on jobs, especially difficult ones, our estimators call in
labor foremen, screed operators and riding bosses to discuss the job
to come up with a competitive bid. We have been seeing increasingly
complex jobs with very tight specs. We researched the equipment out
there, made our purchases based on the jobs we were bidding, and it
has worked in our favor. We are able to complete more complex jobs
faster than what we could have with our present equipment,” he
says.
A
3-D view
In
their research, Vee-Jay employees came upon the Somero S-240 laser
screed. The unit has a 12'-wide head mounted to a 20' telescopic
boom. The 12' head can produce an 8 to 10' strip.
The
four-wheel, all-steer unit takes its orders from an on-board
computer that gets its information from a Trimble AST-600 Series
geodimeter that communicates with the prism placed on the right-hand
mast on the screed. A sonic tracer mounted on the left-hand side of
the screed uses sound waves to follow the edge of the poured
concrete.
“We
first plot the site, then work through the job layout on the laptop,
setting up the slope needed across the job. The computer
automatically figures what adjustments must be made to the screed to
get the slope and flatness we need. It can be accurate to 3 mm. It
will even warn you if you are about to make a mistake,” Barnes
says.
Vee-Jay
put the unit into service early this year. Somero reports it has a
capacity of laying up to 50,000 sq. ft. of concrete a day.
“We
have been using the unit on pours from 14,000 to 42,000 sq. ft. a
day, depending on the job. When we first got the unit, we used it
more as a regular screed, but as we became familiar with the unit,
we use it more and more in its 3-D mode. This machine has opened up
new avenues to do things we used to do by hand and it gives us a
better quality product,” he says.
The
screed has electro-hydraulic controls that direct its movements. The
laptop computer takes the signals it receives from the geodimeter
and translates them into height and directional changes needed to
accomplish the flatness and the slope required. “The hydraulic
control system is a continuous-flow spool so we get smooth, fluid
speed changes. On our older screeds, speed changes are jerky and it
shows up in the pour, but not with this unit,” Barnes says.
For
long and relatively simple portions of a paving job, Vee-Jay crews
use a Whiteman 52' super-screed to lay down concrete. “We then use
the 3-D screed next to these long pours to fill in. The unit also
has zero clearance, so we are able to get up next to buildings. It
has reduced the amount of hand screeding we must do,” he says.
The
unit effectively works in any pour shape, and it doesn’t matter if
you change the direction of the pour in relation to your plotted
area. “The 3-D system is very flexible. On the Boeing job, our
crews laid down strips of concrete with a rolling screed, then came
back and filled in the perimeter with the 3-D screed. The unit
matches existing concrete easily because it takes its reading off
the sonic tracer and matches it up with the geodimeter reading to
produce the right slope while maintaining flatness,” he says.
Tricks
of the trade
In
a trained operator’s hands, the 3-D screeding unit is easy to
operate, and with experience, Vee-Jay and their screed operators are
pushing it to new limits. With experience under their belt, Vee-Jay
offers a few insights:
Have
good operators. “The key is to have good screed operators from the
start and to put them through training. Somero requires a training
class at their facility. Trainees should have some computer
knowledge and be familiar with working with slopes,” Barnes says.
Take
advantage of training. Somero mandates the three-day training
session be taken at their location. According to its Web site, the
away-from-work training gets operators away from normal work
routines so they can concentrate on learning everything about the
system. Near the end of the training, instructors “sabotage” the
machine, giving the newly trained operators a chance to put what
they have learned into practice.
When
plotting, watch for information overload. “The more information
you put into the 3-D Profiler System, the more accurate the pour.
However, you can over-plot sites and give it too much
information,” says Barnes.
Watch
your speed. In most cases, the slower you go, the more precise the
screeding will be.
“Every
pour is a learning experience because every job is so different. Our
operators are very helpful because they know what the machine can
and can’t do.
“We
have found the Trimble 600 ATS series geodimeter and Somero’s 3-D
Profiler System are very user-friendly.
“The
software lets you double-check cross-sections and concrete
thicknesses before the pour begins. We can change it on the computer
before we pour or right in the field. Most changes we make are on
the Z axis (thickness) but we can also adjust the X and Y axes if
there is a problem,” he says.
“This
is a real simple program to use, but for a total screeding system
that costs nearly $400,000, you need a lot of jobs for it. Larger
contractors shouldn’t have a problem keeping a unit like this
busy,” he concludes.
Published
in the January/February 2004 issue of Contractor Tools and Supplies
magazine.
back
to top
|