|
Rebuilding
the Pentagon
The
traumatic events of Sept. 11, 2001, will be forever burned into our
lives and history books. The hijaking and subsequent crashing of
jumbo jets into the World Trade Center, the Pentagon and near
Pittsburgh yielded tremendous tragedy. But at the Pentagon, it could
have been worse.
by Clair
Urbain
Based
on Pentagon press conferences and Department of Defense reports,
when the Boeing 757 crashed into the side of the Pentagon, the
terrorists steered the aircraft into a newly-renovated area. Press
reports peg the plane speed at 345 mph.
“It
was 99 percent complete,” says Lee Benish, of AMEC, the contractor
responsible for the Pentagon Wedge 1 renovation. The company is now
helping with recovery operations and will play a key role rebuilding
the renovated area.
The
Pentagon is made up of five chevron-shaped units that have five
distinct rows of office space that are all five stories high.
The
aircraft also took out a section of Wedge 2, an area scheduled for
renovation this year, says Walker Lee Evey, Pentagon renovation
manager.
The
contrast of the damage between the two wedges is dramatic.
“This
was a terrible tragedy and people lost their lives, but if we had
not undertaken this effort in the building, this could have been
much, much worse,” says Evey, who oversees the nearly $1 billion
renovation that started in 1999.
Two
of Evey’s staff were on the fifth floor of the outermost ring of
Wedge 1, about 50' down the corridor from where the plane entered
the building. In the renovated area, the workers crawled on their
hands and knees and checked every office, from the fifth floor to
the second floor, to make sure anyone who survived could get out.
“They
couldn’t get to the first floor so they crawled out of the
building at that point. This structure held. It did not collapse for
30 or 35 minutes. It gave them the time to do that and it gave
people in the building time to escape the area. We believe that the
effect of the structure was to dramatically slow the plane as it
entered the building and reduce the extent to which it penetrated
the building,” he says. The nose of the plane almost made it to
the innermost circle of the complex. Approximately 3,500 people work
in the damaged area; 189 lost their lives.
Renovation
sorely needed
After
nearly six decades of operation, wear and tear has taken its own
toll on the Pentagon. The utilities are past their useful lives and
the utility distribution system and plumbing cause ongoing
maintenance and safety problems. Ventilation systems are inadequate
and the last time the building met electrical code requirements was
in 1953, says Evey.
Over
the years, communications systems were piggybacked onto old systems,
resulting in a confusing, poorly documented bundle of wires.
Exterior areas of the building are also deteriorating, and asbestos,
lead paint, mercury and PCB contamination throughout the building
make any maintenance job difficult and expensive.
Plans
were laid in 1990 to renovate the complex.
“I
think everyone at some point became aware that our world over the
past years has changed in very dramatic ways and we thought the
prudent thing to do was to recognize that change and take
appropriate steps. We looked at things like the characteristics of
the blast to which the building might be subjected in a terrorist
event,” Evey says.
“No
building can be perfectly safe. No building can be blast-proof. It
can’t be built,” he says.
The
first step taken to improve security was to move all deliveries to a
remote facility at the north end of the building. “The purpose of
that facility is to move truck deliveries, which used to come right
in the south end of the Pentagon, away from the building.
Eighteen-wheelers used to back up inside the building on the loop
itself to unload. This was clearly a tremendous threat,” says Evey.
The
new 250,000 sq.-ft. facility has been open for just over one year.
Once a truck enters the facility, bomb-sniffing dogs check out the
truck and security officers check under the chassis with mirrors.
Everything coming into the Pentagon is examined with pallet-sized
X-ray machines. “After it is checked, it does not leave the
cleared area. It goes through a tunnel to the Pentagon,” he says.
Bus
traffic is also now rerouted to a new Metro station farther away
from the building. “Buses came within 9' of the building. Clearly,
this was something we had to do to help protect the building,”
Evey adds. The building is further protected by an extensive
monitoring and control system through the new Building Operations
and Control Center.
The
exterior high-pressure water lines have also been replaced. “It
doesn’t sound like a safety or security issue, but the last time
we had a significant fire in the Pentagon happened to be on the date
aircraft were going in for their first air strikes on Desert
Storm,” recalls Evey.
A
fire broke out in the basement. When the fire department hooked up
the hoses and turned on the water, the pipes blew and more than nine
million gallons of water flowed into the basement. If the water rose
a few more inches, the Air Force Operations Center would have gone
off-line as aircraft were going in on their initial strikes, he
says.
Logistics
More
than 25,000 civilian and military personnel work in the building;
20,000 personnel must be relocated or worked around at some point of
the renovation process. All building systems must remain
operational, and accessible on all sides and security maintained.
The
building was built in five distinct sections, or wedges, and
that’s how renovation will proceed. “The Pentagon was
constructed in five chevron shapes. Each of the chevrons was built
almost as a stand-alone building. Each has its own utility system
that is separate from the utility systems on either side. That
enables us to build a construction wall, move people out, shut down
the utilities and continue operating the rest of the building,”
Evey says.
New
from the inside out
Each
wedge has over one million sq.-ft. in office space.
Before
the Wedge 1 renovation started, other work had to be completed. The
heating and refrigeration plant was replaced with an
energy-efficient system that offers redundancy. Crews also removed
45,000 cu. yd. of soil from the basement of the building and drove
additional pilings. A new slab and raised flooring provides greater
flexibility and accessibility of the space.
Wedge
renovation starts with relocating workers, then stripping the
internal structure.
From
there, the building’s poured concrete frame is reinforced with
6" x 6" steel beams.
“The
steel beams start on the first floor and go though to the fifth
floor. They’re bolted together floor-to-floor so it is one
continuous unit,” says Evey.
Preserving
the look
The
renovated areas have new windows that match the stripped
neoclassical design of the building, a requirement of the building
being on the National Register of Historic Places. The window design
preserves the look of the original building, but is built to take a
much greater blast impact. The glass in the blast-resistant windows
is almost 2" thick. More than 1,500 windows were replaced in
Wedge 1 renovation.
The
Army Corps of Engineers helped develop the steel framework that goes
around each window to offer improved blast protection. Each
blast-resistant window system weighs 2,500 lbs.
In
the attack, many of the new blast-resistant windows did not shatter
despite the enormous pressure placed on them, Evey reports.
Conversely, many of the old windows in the unrenovated Wedge 2 area
were shattered, even at great distances from the point of impact.
White
Kevlar fabric installed between the frame’s exterior and the
building skin provides additional protection.
“That’s
the same stuff found in bullet-proof vests. We interspersed it
between the steel beams and the windows to catch any fragments that
would result from a blast event,” he says.
|
Pentagon
facts:
•
Completed in 1943
•
Built in 16 months on a 24/7
schedule with 400 architects and
engineers and 15,000 workers
•
Original cost: $83 million
•
435,000 cu. yd. of concrete
•
42,240 support columns
•
34 acres
•
6.5 million sq. ft., equivalent to
three Empire State Buildings
•
7,748 windows
•
17.5 miles of corridors
•
30 miles of roads, bridges and
access ramps
•
25,000 personnel work in the
complex
•
Projected renovation cost
(before attack) $900 million+
•
Estimated completion date: 2012 |
“From
evidence in the area, we believe this structure dramatically slowed
the plane as it entered the building and reduced the extent to which
it penetrated it,” Evey says.
“As
the plane entered the building, it sheared off or severely damaged
supporting columns. What held up a portion of the building are the
steel columns we put in. Had it not been for them, you would have
had a much larger collapse and perhaps many more casualties,” Evey
says.
Fire
sprinklers were also installed in the Wedge 1 renovation. “There
was a fire that raged through Wedge 2, the unrenovated area. If you
look at Wedge 1, except in areas where it was clearly fueled by jet
fuel, the fire was knocked down by the fire sprinklers. There was no
spread whatsoever,” he says.
Change
in acquisition process
The
Pentagon’s new attitude includes a new thought process on contract
work. Long driven by a low-bid philosophy, the Pentagon will use
design-build concepts for Wedge 2 through 5 renovations.
“We
wanted to go about our work in a different way. Wedge 1 was built in
the traditional manner where you hire an architectural engineer who
does designs, drawings and specifications for you. For Wedge 1, that
set of drawings was 3,500 pages. It’s very elaborate.
“After
you have those drawings and specifications done, you put the package
out for a bid and you get a contractor to build to what the drawings
say. What we are doing with Wedges 2 through 5 is called
design-build. We hire the architect/engineer and construction
contractor as one package and they work as a team. It dramatically
reduces the number of specifications and drawings that we provide.
We ask them to provide a certain output product that we call a
performance specification,” he says.
In
contrast to the 3,500 pages of documentation for the
design-bid-build process, Evey says the documentation for the
design-build process for Wedges 2 through 5 is only 16 pages. “We
have done it several times in the Pentagon renovation. It saves
taxpayers money. It saves us time,” he says.
Wedge
1 renovation begins again
Rebuilding
Wedge 1 will continue under AMEC, the present contractor. The Wedge
2 through 5 renovation will proceed as planned by Hensel Phelps
Construction Co., says Evey. “The initial value for Wedges 2
through 5 is $145 million, which is the monies we have available
this year. The total potential value is $758 million,” he says. It
does not include the funds needed to bring Wedge 1 back to its
pre-bombed status.
Published in the
November/December 2001 issue
of Contractor Tools and Supplies
magazine.
back
to top
|