|
The
second straw
Las
Vegas has an unquenchable thirst for water; the Southern Nevada
Water Authority’s Capital Improvements Program will double water
treatment capacity to almost one billion gallons a day.
by
Clair D. Urbain
There
is much more at stake in Las Vegas than bets in the casinos.
It’s
water. The Southern Nevada Water Authority (SNWA), made up of seven
water and wastewater agencies in the Las Vegas metropolitan area,
have combined forces to meet the burgeoning demands of the growing
population.
“More
than 5,000 people move to the Las Vegas area every month and we have
39 million visitors annually. It’s the fastest growing area in the
United States and to obtain water in a desert region takes planning,
engineering and construction to keep up with the demand,” says
Robin Rockey, SNWA project information manager.
SNWA
and Parsons, the company overseeing design and construction of the
project, helped the authority develop the $2.1 billion capital
improvements program, says Bill Buchholz, Parsons’ project
officer.
“The
goal is to create a system that will reliably provide the burgeoning
SNWA area with water. One strategy was to establish uniformity in
the system – treatment plants, pumps and system designs – for
efficiency and reliability,” Buchholz says,
The
area’s fast growth meant the well-thought out plan had to be
expedited. “Because of explosive growth, the plan for 2014 had to
be completed in 2006. This has been a strain on everyone involved
with construction,” he says.
The
project began in 1991 and is approximately 85 percent complete. Lake
Mead is the source of more than 90 percent of the area’s water and
a second intake is in place and connected to the water treatment and
pipeline system. The new intake was put into service in 2002. It’s
dubbed the “second straw” Las Vegas has into Lake Mead, the
man-made lake behind Hoover Dam.
The
second intake draws water from as deep as 230' below the lake’s
surface. From there, water flows to a forebay through a 1,700' long
x 14' wide x 16' high tunnel. In the forebay, 3,000-hp turbine pumps
fit in 22 72" diameter well shafts with 50" casings. At
capacity, the pumps can draw up to 600 million gallons a day (mgd)
and pump it through a 12'diameter aqueduct to the Alfred Merritt
Smith Water Treatment Facility adjacent to Lake Mead, or through the
mountains to the newly constructed River Mountains Water Treatment
Facility near Henderson. After treatment, the water is pumped to
municipal reservoirs. When complete, the system will be capable of
delivering 1.2 billion gallons of treated water every day.
Back
to Lake Mead
With
that much water coming into a desert area, where does it go once
it’s used? Treated wastewater flows through the Las Vegas Wash,
which meanders across the desert and delivers it back to Lake Mead.
“Las
Vegas is one of a very few cities that lives downstream of its own
wastewater,” says Buchholz. The SNWA gets credit for water it
returns to Lake Mead, further upping its ability to draw fresh water
from the lake.
Two
water treatment plants process water for the valley. The Alfred
Merritt Smith plant, on the shores of Lake Mead that processes up to
600 mgd, was completed in 1997. To transport raw water to the River
Mountain plant, the East Valley Lateral was built in 2000. It
includes a 78" diameter pipeline that crosses beneath the Las
Vegas Wash. “The pipeline required extensive tunnel-boring under
the wash to assure a rainfall event would not erode it,” says Joe
Pescio, Contri Construction project manager.
The
tunnel under the wash is 1,500' long and is just upstream from the
Rainbow Gardens weir project. “It’s 60' below the base of the
wash, so it is protected from any type of rainfall event,” says
Pescio. “It is hard rock, so it was a tough drilling job. The
pipeline was a rather straightforward job. It runs close to existing
utilities and another water line. To assure there would be no damage
to existing infrastructure, the pipeline path was closely marked and
potholes were dug ahead of crew to every 200' and at every bend to
assure no utilities would be hit,” he says.
Due
to high flow rates from Las Vegas area wastewater treatment
facilities and high rainfall events, erosion takes its toll on the
wash, damaging the wetlands along the wash and carrying unwanted
sediment flows into Lake Mead. To counteract the erosive effects of
high water flow and give sediment a chance to settle before reaching
Lake Mead, several weirs (dam-like structures) and other water
control systems are being installed all along the wash.
“The
Rainbow Gardens weir work was bid as part of the East Valley Lateral
project, which is the last full weir before the water enters Lake
Mead. It also serves as the final water flow measurement point used
to calculate the amount of water returned to Lake Mead for credit to
the SNWA,” he says.
“It
made sense for us to work on the weir because we were in the area,
which increased efficiencies. The jobs all along the water project
are fairly spread out. It can take up to 20 miles of travel between
jobs, so you really need to plan what tools you need before heading
to the job,” Pescio says.
Tying
the East Valley Lateral into the River Mountains Water Treatment
Facility created challenges. “The existing pipeline had
non-standard connections. We had to connect to a tapered pipe at an
angle. We surveyed both ends of the pipe very accurately, then had
the connection built.
“When
it came time to connect it, we put together a plan. We had a list of
all the equipment needed plus backup equipment. We had to shut down
and drain part of the system, so we made sure all of the reservoirs
were full and that contingency plans were in place if something
didn’t go right,” Pescio says. “We planned to finish the
connection in 24 hours, but we were able to do it in 12 hours. The
amount of planning was three or four times greater than for a normal
connection.”
At
the weir, construction was more difficult. “The Rainbow Gardens
weir was tricky to build because it is an active wash. We had to
build a dam and divert the flow around the work area,” says Pescio.
Pescio
and his crews paid close attention to rainfall forecasts and water
flow measurements upstream. “We had significant rainfall events
during construction. Luckily, none were 100-year events. The
diversion could handle 5,000 cfs, and during construction we had
only one event that approached 3,000 cfs. We recently had a 10,000
cfs event and we were lucky to be finished and out of there,” he
says.
The
weir is built with roller-compacted concrete. “The mix is very dry
and put in place with a telescoping conveyor, then smaller-sized
construction equipment formed it into place and compacted it. It was
a tight working area, so we used a mini-excavator for prep work,
then used aluminum beams and plywood for forms,” he says.
Fast-track
water treatment facility
Of
the more than 100 individual projects included in the SNWA’s
construction program, perhaps the fastest moving project is the
River Mountains Water Treatment Facility. The facility is designed
to be built in 150 mgd sections. The first two sections will be
finished late in 2005 for an operating capacity of 300 mgd, nearly a
decade earlier than planned.
The
nearly $250 million project is slated for completion in the Fall of
2005. Phase 2 construction has been underway since July 2003.
“While
the buildings and infrastructure were built in Phase 1, the Phase 2
project takes present plant capacity of 150 mgd to 300,000 mgd.
It’s mostly pipe-fitting and controls work. Tying the new system
into the Phase 1 system is challenging,” says Blaine Stewart, job
superintendent for MMC Inc., which is in charge of Phase 2
construction at the water treatment facility.
Crews
have already tied the second 150 mgd section into the first section
put in operation during Phase 1. It required tight planning and
clockwork-like activity.
“We
only had 13 days to tie the second section into the first one,”
Stewart says. “This was an almost completely confined-space job.
It took five days to drain the tanks and have the ozone levels drop
to a point where the tanks could be entered safely.
“Workers
began on the new side of the facility by coring holes to within
2" of breaking through the walls. Once ozone levels were low
enough and the tanks were drained, we cored the remaining thickness
and then brought in a wall saw to cut out the 12' x 6' holes in the
16"-thick concrete walls. The pieces were cut again into 3' x
3' sections and pulled out of the holes by crane. We continuously
monitored the confined areas for ozone and high oxygen levels with
badges and monitoring equipment. If ozone levels get too high, it
can burn workers’ lungs,” he says. “We tried to do as much
work as possible on the new side.”
The
Water Treatment Facility is made up of a flow split structure that
takes water rushing in from the River Mountains Tunnel, slows its
velocity, then transfers the raw water into water processing areas.
The
first stop for the raw water is the ozone contactor area, where
ozone bubbles through the water and disinfects it. From there, it is
pumped to the flash mixing and flocculation basins where materials
are added to coagulate microscopic particles which separate out in
the filter galleries. At this point the water is treated with
fluoride, chlorine and other chemicals to make it safe for drinking.
“We
only had 1/2" of clearance to move pipes and valves into the
filter gallery,” says Stewart. “We had to be careful of the
equipment weight to make sure it wasn’t too much for the
weight-bearing capacity of the gullets. We were right at crane
capacity when we flew in the 48"-diameter x 38'-long top pipe
in the filtration facility. We also had to cut the 48"-diameter
pipe already in place to install a two-sleeve valve so a bypass
valve could be installed to allow back-flushing of the filter
beds,” Stewart says.
Jobsite
safety
To
date, there have been 196 recordable incidents since construction
began and only 55 were lost-time incidents on the entire project
since 1995. The overall safety record is excellent, report SNWA
officials. The recordable incident rate for the program is less than
two-thirds the national average and the lost time incident rate is
less than half of the national average.
“Our
contractors have safety meetings every Monday to discuss the work
and point out safety concerns for the coming week. There are some
language barriers. We now do some safety meetings in Spanish. We
have some workers who cannot read, so they are more challenging to
train. For others, safety is not a big part of their work ethic, and
we work with them to change that,” says Buchholz.
Every
worker gets nearly a half-day of general training before commencing
work on any SNWA site. Every worker must go through desert tortoise
training, which helps protect this endangered species found on
SNWA’s properties. Workers are instructed on the importance of the
18"-high tortoise fences that line the roads and access points
to keep the tortoises out of danger. U-troughs planted across
entrances keep the tortoises corralled in areas where fencing is
impractical.
Published in the
May 2005 issue
of Contractor Tools and Supplies
magazine.
back
to top
|