|
Compressing
time and space
How
contractors squeeze time and space to gain value in San
Francisco’s hot real estate market
by
Clair D. Urbain
There
was a time when constructing a large building could take up a
substantial portion of a construction worker’s life. While some
projects take five or more years to build, today’s projects are
based on finding ways to compress time and capitalize on building
space to yield the most usable (or leasable) space in the shortest
amount of time.
Field
foreman Don Reilly, a second-generation electrician, has been in the
business for more than 25 years, and Rob Hupp, a fourth-generation
electrician with 12 years of experience, are working for Cupertino
Electric Inc. (CEI) on the fast-track, design/build Hotel Vitale
project in downtown San Francisco.
“My
father was an electrician on the Wells Fargo Bank building built in
1967. That 50-story building took almost four years to build. Now,
the same building can be built in two years. That compression in
time helps owners get buildings on the market sooner,” he says.
Time
is not the only price driver on this job. Real estate in downtown
San Francisco fetches top dollar. The hotel is on the corner of
Mission Street and the Embarcadero, the busy district that runs
along the bay. The site was once a municipal parking garage, but the
city, realizing the value of the property, signed a 65-year lease
for the land with developers and construction crews broke ground in
January 2004. In a little more than one year, what was once a
municipal parking lot is now an eight-story upscale hotel with
dramatic views of the San Francisco Bay. The plan calls for the
hotel to greet its first guests before March 2005.
Design/build
pushes the envelope
CEI
subcontracts the electrical work on this project; Webcor is the
general contractor. “This is a design/build job. It’s a
199-room, 143,000 sq. ft. facility with a 3,000 sq. ft. lobby
lounge, a 3,200 sq. ft. restaurant and two conference rooms on the
first floor. Another 1,100 sq. ft. of the ground floor is retail
space and restrooms for municipal bus drivers,” says Reilly.
To
get the most use from the space, the building’s design takes the
concept of shoehorning to new levels. “In older multi-floor
buildings, you would commonly see 15' floor heights. In this
building, the floors are only 9', which means we can get 40 percent
more floors in the same building height,” Reilly says.
To
save space, the building uses its ceiling spaces as an air plenum.
“Each floor’s corridors are fire-rated and are used to help move
fresh air through the building. There are toilet exhaust fans in all
rooms that pull fresh air from the hallways into the rooms. These
units are on emergency power circuits so they will operate even if
there is a power failure,” says Reilly.
Room
HVAC is part of a closed loop system. “The rooms are smaller and
the water-cooling and heating technology is much more energy
efficient than standalone electric units used in many hotels,” he
says.
Like
other design/build projects, engineering drawings are made nearly on
the fly. “We have had 400 changes on this project since its
inception. We made design decisions even during the concrete
pour,” he says.
Rob
Hupp, electrician foreman, has experienced the tight quarters and
design-on-the-fly approach firsthand. He is responsible for roughing
in all conduit from the underground excavation up through the
building as concrete was poured.
“This
building was constructed with 27 different pour intervals. Each pour
was about 12,000 sq. ft. that took place every four days,” says
Hupp. Once the pours were complete, rooftop mechanical equipment was
placed earlier than usual because the crane and manlift had to be
taken down to make more room on the site.
“The
challenges started right with the underground work,” recalls
Reilly. “There was a building on this site before the earthquake
in 1906 and we ran into the wooden piers below ground when driving
piles. The piles had to be redesigned, and that pushed the project
back 10 weeks. It required us to reroute electrical service and made
us work around an underground seawall. In one area, the footings
must cantilever support over the seawall because it is in the
way,” he says.
Hupp
says laying in the underground electrical work was difficult. “We
had lots of rain throughout the foundation work. Because the site is
so compact, we only excavated 10' at a time to keep working yet stay
out of the way of other trades working in the same space,” Hupp
says.
The
architectural design calls for 13 distinct roof levels, some of
which are public spaces that require emergency lighting, monitoring
and fire warning systems. “Working with roofers to make sure all
stub-ups were installed was like working on 10 jobs at once,” says
Hupp.
The
elevators use a space-saving design that reduces their mechanical
room footprint. “The elevators use a penthouse that is only
10'x14', about half the space of a conventional penthouse,” says
Reilly. In this design, elevator power unit controls are located
outside of the penthouse. To service the unit, workers ride on top
of the car that acts as a lift to the mechanical portion of the
elevator. “This is cutting edge – the state of California is
still reviewing it. The benefit is lower cost and it preserves
square footage for other uses,” Reilly says.
Now
that the building is up, space continues to be at a premium. “The
delivery area for the building is only 20'x80', so we must work with
other subcontractors to schedule deliveries. There is so little
storage area on the jobsite that we must have materials delivered
only when we need them,” he says.
All
mechanical rooms are very tight quarters. The electrical rooms on
the roof are only 6' wide and must meet all codes for clearance and
safety. “In one room, a support beam comes through in such a way
that we couldn’t install the switchgear with the wiring access
behind it and still maintain aisle width and clearance requirements.
To accommodate it, we added a side can to the switchgear. This gives
us narrower switchgear that meets code requirements,” says Hupp.
The
phone system, which was originally positioned on the first floor,
was moved to the second floor, sharing space with that floor’s
electrical room. This change was incorporated after the conduit for
the incoming line was laid in concrete. “We worked around it by
taking the main lines back through conduit in the floor and then
through other conduit to the second floor,” says Hupp.
On
the roof, electrical closets are so small that transfer switches and
motor starters are located outside the rooms. “Each motor has a
disconnect switch on it, but the motor starters are outside to help
gain space in the 20'x40' rooms,” Hupp says.
Topping
and finishing off
As
work crews neared finishing pouring concrete on the top floors,
follow-up crews began on the lower levels pulling wire and
installing lighting, smoke alarms and receptacles. From data cables
to the remote controls for the automatic shades in the luxury
suites, finish foreman Robert Taylor and his crew tie each room’s
amenities into the grid.
“As
the upper floors are roughed in, we are finishing the floors below.
We wire in the rooms to the main panel on the floor then lock out
all but the temporary circuits. Once the floor is completely wired,
we test everything and have the floor inspected. Once it passes
inspection, we go to full power on the floor and remove the lockouts
on the rooms,” he says.
To
speed installation, Taylor relies on apprentice electricians to
pre-wire all fixtures with pigtails as long as 10', and then pull
them into their locations. Once wires are pulled, the fixtures are
mounted and connected to circuits.
With
many trades working one area, there have been instances of crews
drilling through slabs and hitting other mechanicals in the process.
“In this type of a fast-track design/build project, some of that
is unavoidable,” says Hupp.
Heading
off problems
The
design/build process redefines the project specifications on the
fly. With it comes the chance for mistakes. To date, Hupp says they
have only missed the correct location of one hole for conduit
placement. He credits much of that success to Reilly’s attention
to detail.
Reilly
gets job drawings that are 50 to 75 percent complete and reviews
them with the engineer. “I redline them and the engineer goes back
and puts them in with CAD and produces the construction
documents,” he says.
Published
in the January/February 2005 issue of Contractor Tools and Supplies
magazine.
back
to top
|