|
Terminal
progress
Building
the new Midfield Terminal at the Southwest Florida International
Airport in Fort Meyers, Fla., puts contractors, work and schedules
against tight constraints. Here's how the job is staying on
schedule, on budget and safe.
by
Clair D. Urbain
The
20-year-old terminal at the Southwest Florida International Airport
is a comfortable, friendly and, by most standards, modern facility.
It’s also busting at its seams.
In
the last decade, the population in the Fort Myers metropolitan area
grew 39 percent. Today, almost six million passengers stream through
the facility that was designed to handle no more than three million
visitors annually. With that much traffic, it adds new meaning to
the word overbooked.
New
Midfield terminal
Lee
County Port Authority (LCPA), which operates the airport, set out to
increase terminal capacity. Although today’s 381,000 sq. ft.
terminal with 17 gates is still relatively new, an in-depth study
proved a new terminal was the best way to meet today’s congestion
and tomorrow’s projected growth. Its solution was to build a $438
million, nearly 800,000 sq. ft. terminal south of the existing
runway. It will have 28 gates on three concourses with room to
expand concourses, plus the option to add concourses, for a total
capacity of up to 65 gates.
“The
terminal is scheduled to open in April 2005, and is designed to
handle the steadily growing number of passengers, flights and
increased post 9-11 security measures,” says Joe Glowacki,
construction manager for DMJM Aviation,
LCPA’s project representative.
“This
has been an interesting project from the beginning. From site
preparation to tying new taxiways into the runway, it requires
coordination and communication to stay on schedule,” he says.
The
project is split into nine segments, with similar work on different
areas put together in bid packages. Each segment was awarded as a
separate prime contract, with Dick Corporation acting as the prime
contractor for the terminal building construction.
“From
design through construction, we have zoned the work to be able to
coordinate construction,” says Glowacki. “That helps us keep
contractors working side-by-side with as few interruptions as
possible. That gets even more important as work concentrates in the
terminal and concourses,” he says. The project is nearly 60
percent complete.
Site
preparation
Site
work started on the project in early 2002, with Phoenix Construction
Services of Lynn Haven, Florida, building up the elevation of the
terminal and parking areas on the 1,200 acre site. “The area
surrounding the airport had to be raised by as much as 3',” says
Glowacki. “Almost all of the fill, which totals 3.5 million cu.
yd., was excavated from an area south of the facility that is now a
12'- to 15'-deep, 240-acre lake for storm water control,” he says.
To
handle the water runoff from the facility, 92,500 linear ft. of
drainage funnels rainwater to two canals that carry it to a dry
settling area before it is released into the newly created lake. The
water is held here until it is eventually released into the county
water management system.
Much
of the new site was in low-lying wet areas. The airport and
designers compensated for any wetlands that had to be filled by
initiating a 7,000-acre mitigation park project that creates fresh
water marshes and enhanced uplands in an adjacent wildlife refuge
corridor.
Foundation
and road work
While
three engineering firms worked on separate parts of the project, the
foundation work was awarded to one contractor. “This is a case
where we wanted to get bids for work that was similar, so we put the
foundation work for the upper-level roadway, terminal and parking
garage together,” says Glowacki.
PCL
Construction Services of Orlando started piling work in September
2002 after an extensive soil sampling and study. In all, the
contractor placed more than 5,000 pilings from 14" to 24"
in diameter up to 80' deep for the facility.
To
handle traffic, Better Roads, Naples, Florida, is building a new
3.7-mile road to the new terminal.
“Construction
traffic uses roads set apart from the roads used by the present
terminal,” says Glowacki. “All construction is outside of the
secured area of the airport, so we don’t need extensive security
checks on workers.”
However,
the site is guarded 24 hours a day and construction access is
severely limited. Any worker coming on the site must have a sticker
on his or her hard hat that shows the worker has been through the 1
1/2-hour safety orientation. “We do not allow anyone to work on
the site without going through training,” says Glowacki. “It’s
part of our owner-controlled insurance program (OCIP). We think it
greatly reduces injuries on the site.”
While
jobsite traffic is away from airport traffic, DMJM Aviation also
wanted to minimize worker traffic close to the jobsite. It
established a 30-acre job trailer, parking, supply and equipment
staging area a few minutes from the site. “We have a bus that
takes workers to the site. We don’t have any of the workers’
vehicles parked around the job. Because job trailers are in a secure
area, we have had no problems with theft or property damage,” he
says.
Air
side connection to the runway
While
anyone on a construction project can conceptually relate to being up
to their you-know-what in alligators while trying to drain the
swamp, Steve Monks, project manager for John Carlo, Inc., can relate
to it quite literally.
This
contractor is responsible for the flatwork on the air side, land
side, elevated parkway and flat parking areas on the job.
Monks,
who has worked extensively in Canada, is more familiar with
freeze-thaw cycles than the high groundwater table and the many
species that call the Florida swamps home. Instead of freezing
temperatures, his crews must deal with sub-tropical rainstorms that
can halt taxiway and apron construction for days. “This is a
1,200-acre site with many open ditches. We do much of our work at
night, so we must check the site for alligators and snakes. We have
not had a direct problem, but they are out there and we must always
check for them before we start work,” he says.
“Last
summer had particularly heavy rains. We had 30" of
precipitation from August 30 to September 28. Florida is so flat
that when it rains heavily as far as 100 miles away, it flows like a
sheet and it eventually affects your job. We regularly use 12"
pumps to get water away from the site so we can continue with flat
work,” he says.
On
the air side, tying the taxiways into the runway requires precise
coordination with the FAA, but the heavy rain in 2003 and tight
security and safety requirements allowed the crews to complete only
seven of the nine taxiway tie-ins to the runway. “When the last
flight goes out at night, we have until the first flight in the
morning to work on the taxiway. It’s like a city street. It must
be open in the morning,” he says.
“We
are front-loading the rest of our work, increasing the earth-moving
crews to get most of it finished before May. We want the earthwork
to be done on the air side, land side and garage parking areas so we
can work wherever it’s fit,” he says.
Increased
security changed design
Design
work on the Midfield Terminal building was nearly complete when the
Transportation Security Administration and the FAA required
extensive – and expensive – screening systems for passengers and
their baggage. “This caused the project to go back into design to
accommodate all of the security equipment,” says Glowacki. “In
the end, it added a 27,000 sq. ft., 30' x 900' addition in the
baggage-handling area for additional security equipment. It also
meant redesigning passenger check-in and screening areas. That
required close coordination with the designers and the
contractors,” he says.
Nearly
1,000 workers within 1,000'
With
work on the terminal building progressing rapidly, Glowacki says the
site will average 800 workers per day for a wide variety of
specialty trades. That requires exceptional coordination and
communication, he says.
The
terminal is divided into 12 zones with each concourse separated into
four zones. “We track work progress in each zone, releasing
control of any zone from one type of contractor to another to
minimize congestion and improve safety. We meet with the general
contractors every week to discuss progress and safety issues as the
construction progresses. It has been working well,” he says.
To
assure a safer workplace, the LCPA hired Arthur J. Gallagher &
Co. to coordinate its owner-controlled insurance program (OCIP),
says Lenore Morrill, OCIP insurance coordinator for Arthur J.
Gallagher & Co.
“OCIPs
are more popular on the West Coast, but we are seeing more of them
on the East Coast and in Chicago as well,” says Morrill. “They
are great for projects greater than $100 million. These tend to be
public projects with many contractors involved, most of which could
not afford the insurance needed on such a large project. This also
allows smaller contractors to be a part of the project,” she says.
Under
an OCIP, consistent safety measures are put in place and enforced
across all contractors. It also offers medical coverage for any
injuries and general liability coverage with a five-year tail in
case a contractor goes out of business.
“Insurance
companies like OCIPs because they help control costs at the front
end with good management so litigation isn’t needed later in the
project," she says.
Part
of the OCIP requires that every worker on the site completes a 1
1/2-hour safety orientation before they set foot on the jobsite for
the first time. Bill Wojtkowski, OCIP safety director employed by
Construction Safety Services, Inc., conducts the safety orientation
at least four times a week.
When
a worker completes the training, which is available in English and
Spanish, he “labels” that worker’s hard hat with a sticker.
“No worker is allowed on the site without a sticker,” he says.
During
training, Wojtkowski uses a variety of teaching methods to get
safety messages across. “Illiteracy is something I watch for. If
any worker has trouble with the material, I will work with that
person one-on-one to assure he or she knows what we expect in the
way of safe behavior.
“The
most important thing I stress is that unsafe behavior is not
tolerated, and there are consequences. I also reinforce that I am a
resource to help them do their job safely. If they think a task is
unsafe, it probably is and I am here to help them find a safer way
to do it. I want to motivate them as a coach and have them police
themselves. It’s more effective than relying on my constant
presence,” he says.
Contractors
meet every other week to discuss specific safety concerns. “This
job changes every day and we have had more than 5,000 workers go
through our training program,” says Morrill. “That means there
is lots of turnover and the job is a moving target. With 800 workers
on a job on any day, there will be some incidents, but we have had
far fewer of them and no major injuries or deaths.
“Any
contractor with more than 20 employees on the site must have a
full-time safety person on the job. They are also required to attend
bi-weekly safety meetings,” she says.
Wojtkowski
tours the site daily. As he audits work, he will write infractions
to workers for unsafe practices. “If a worker is cited for doing
an unsafe work practice, that person will receive a one-, two- or
three-day work suspension, depending on the seriousness of the
violation or the number of past offenses. With three safety
violations, the worker is banned from the site forever.
“We
have had near-misses. A fall-arrest system saved a life and safety
glasses saved an eye or possibly even a life. This illustrates the
importance of a proactive safety program. There are no exceptions;
even people from DMJM Aviation and members of the board of county
commissioners must follow our rules. It’s the only way to keep the
site as safe as possible,” he says.
“This
safety program is supported from the top and they are depending on
it to make this a safer jobsite and to allow a job of this magnitude
to be completed. The OCIP allows disadvantaged business enterprises
to be a part of the job. We have lots of heavy construction going on
and it can be very dangerous work. That is why a no-tolerance
program is essential,” says Morrill
Published in the
March 2004 issue
of Contractor Tools and Supplies magazine.
back
to top
|