|
Say no to crack
Follow these
suggestions from the Portland Cement Association to minimize random
cracking on your next concrete pour.
by Paul Markgraff
Owner complaints lead to
rework, and rework costs money. One of the most common complaints
contractors hear is about cracked concrete.
However, concrete is
supposed to crack. As it transforms from a liquid into a solid, it
shrinks and cracks. It's natural behavior of the material.
Contractors can’t
prevent concrete from cracking, no matter how hard they try. But,
random cracking can be minimized.
“That’s why we put
joints in concrete,” says Terry Collins, concrete construction
engineer for the Portland Cement Association (PCA). “We know it’s
going to crack, and joints provide a weakened plane or planned
location for the concrete to crack in such a manner that the
concrete will perform consistently and structurally.”
Focus on random cracking
is important to understand because every piece of concrete in a
building has cracks, says Collins. But there are strategies
contractors can use to reduce random cracks that cause customer
complaints.
Shrinkage?
Shrinkage is a fact of life when it comes to concrete. When
contractors place concrete, there is a certain amount of water
beyond what is required for cement hydration. This water lubricates
the mixture and helps the contractor place, consolidate and finish
the slab.
“Because the water is
the lightest material in the mixture, it rises to the top,” says
Collins. “The water that comes to the surface and collects there is
called bleed water. That water evaporates into the air.”
Direct sunlight, high
temperatures, low relative humidity and wind accelerate the rate of
bleed water evaporation. When water evaporates from the surface
faster than bleed water can accumulate, the surface begins to dry
and crust.
“As it crusts, it
creates a surface tension across the entire mass of concrete,” says
Collins. “This shrinkage is exhibited as a series of cracks running
parallel to each other on the concrete surface.”
Contractors can use
three strategies to combat shrinkage on a concrete slab. The first
is fogging or misting. Contractors can apply moisture at the surface
of the concrete to satisfy that rate of evaporation while the
hardening of the concrete below comes in line with the surface, so
the concrete is consistently set through its depth.
“Misting can be done
with something as simple as a hand sprayer,” says Collins. “If it’s
a very large surface area, you may need something like a pressure
sprayer to reach all sections of the slab.”
Contractors must treat
the water they spray like they would treat regular bleed water. You
can’t trowel the surface while it is covered in water, or you will
add energy to the system. This will change the water/cement ratio at
the surface and weaken the concrete, resulting in more cracks.
Contractors can also
cover the surface with plastic sheets, which protect the moisture
content of the concrete from rapid evaporation. This can slow the
rate of evaporation to acceptable levels.
“When you pull the
plastic, you need to allow that sheet of water to come off,” says
Collins. “You’ll remove a light film of cement paste when you do
this, but it’s minimal.”
The third strategy
involves using chemical evaporation retarders, such as concrete
films. These are spray-applied and formulated to evaporate more
slowly than water. The water in the chemicals will eventually
evaporate. During drying, the chemicals turn into a protective film
that minimizes plastic shrinkage and cracking.
Don’t settle for less
There are two types of settlement cracking. The first results from
the irregular settling of the base material that supports the
concrete which can cause unusual stress points in the concrete above
and eventually causes the slab to bend.
“As it bends, the
concrete goes into tension at the base. Under the load, and at the
weakest point, it will crack,” says Collins. “At some distance from
the load, the settling creates surface tension in the concrete
because the load-bearing soil beneath it is resisting the bend.”
Concrete can stand
substantial vertical pressure. It takes 4,000 psi to crush a
concrete test vessel, but it only takes 8 percent to 10 percent of
4,000 psi to overcome concrete’s tensile strength, or its horizontal
strength, under vertical pressure.
“Good preparation of the
sub-base that supports concrete can minimize this type of cracking,”
says Collins. “The concrete’s job is to transfer the load to the
larger area of soil underneath it. Most of the time, this type of
cracking results from poor compaction of the base material before
concrete pouring.”
Contractors may be
surprised to learn that the density of the soil compaction is not
the major factor of base support. Rather, the consistency of the
soil compaction makes the most difference when trying to prevent
this type of cracking.
The other type of
settlement cracking involves steel reinforcement and placement. As
the concrete bleeds and the extra water in the mix rises to the
surface, heavier particles in the concrete descend to take that
water’s place. In a steel-reinforced slab, this dynamic pulls some
of the concrete away from the steel reinforcement, creating a small
void between the rebar and the concrete. This type of settling sets
up circumstances under which rebar can oxidize and concrete will
crack.
“Good consolidation will
minimize this problem,” says Collins. “When contractors shake the
slab with an external or internal vibrator, the concrete starts
behaving like a liquid. Heavier particles settle and lighter
particles rise to the surface. This is called liquefaction, and air
and water rise to the surface rapidly under these circumstances.”
Crack inducement
Cracks are going to happen, so what better way to minimize random
cracking than by inducing these cracks intentionally before they
surface accidentally?
In general, contractors should put joints in concrete slabs at a
distance of 24 to 30 times the thickness of the slab. Then, cracks
will end up where you placed the weakened plane. For example, if you
have a 4"-thick slab, you would multiply 4" by 24 to get 96", or 8'.
This means contractors should place a joint once every 8' when
laying slab.
With larger, 1" coarse
aggregate, contractors can extend the distance between joints to 36
times the thickness of the slab.
“Regardless of the
thickness of the slab, you should not exceed 15' between joints
unless you are going to provide load-transfer devices such as dowels
or dowel plates,” says Collins.
A time and a place
Contractors must also be aware of the raw materials and weather
patterns of the area.
Concrete is usually made
of locally available materials. For example, in central Nebraska,
concrete tends to have high sand content because they have miles and
miles of sand, but not as much stone, Collins says.
When contractors use
sand in the cement mixture, they are using a very small aggregate
with a high amount of surface area. More cement paste and water are
needed to coat every single grain of sand. This increases the
potential for cracking because more water has been added to the
system.
“If you have an even
gradation of aggregates – meaning large particles, medium particles
and small particles – then you have a very small void content,” says
Collins. “You don’t need as much cement paste, and as a result, you
don’t need as much water. Bad gradation, small aggregate size and
high volumes of sand increase the water demand and the potential for
shrinkage.”
Concrete placed during
hot midday temperatures contracts as it cools overnight. A 40 F
swing in temperature between day and night – not uncommon in many
regions – would cause a 0.03" contraction in a 10' length of
concrete. This will create cracks if the concrete is restrained in
any way.
“You should take a look
at the high and low temperatures and time your concrete placement
for the middle of that window,” says Collins. “In a warm-weather
climate, you may not want to place concrete at 8 a.m., because the
outdoor temperature will hit its peak just as you finish your pour.”
An early-evening pour
can work well because temperatures usually don’t swing as much
overnight.
“Varying the time of the pour to hit the middle of the temperature
swing can really help minimize cracking due to shrinkage,” says
Collins. “However, this can be problematic for a contractor, because
he or she has to pay his workers overtime if they come in at night
to do this kind of job.”
Published
in the March/April 2008 issue of Contractor Tools and
Supplies magazine.
back
to top
|